Use the 'Forecast to Complete' Feature
Background
To ensure that future activities and costs on your project remain accurate and consistent, it is important to actively manage and monitor your project's budget. If that activity is your responsibility (for example, if you are a project manager or project accountant), you may need to generate weekly or monthly reports to clearly account for all your project's billable costs (in other words, what has been completed on the project) and projected costs (in other words, what remains to be completed on the project).
To help your project team gain a greater understanding of what remains to be completed on a project, a 'Forecast to Complete' column is included, by default, on several of the Budget tool's 'Standard Views' (for example, Procore Standard Budget, Blank Budget View, (Multi-Level) Procore Standard Budget, Procore ERP Direct Cost Budget, Procore Standard Forecast, and Procore ERP Direct Costs Forecast). This column can also be added to any customized budget or forecasting views that you choose to create. See Set up a New Budget Viewand Set Up a New Forecasting View.
With the 'Forecast to Complete' column, you can:
Estimate the 'Projected Over/Under' cost for each budget line item
This ensures that the total in the 'Estimated Cost at Completion' column is accurate and consistent with your previous weekly or monthly projection.Choose the calculation method to apply on a per-line-item basis
The Automatic Calculation setting calculates the remaining project costs by subtracting the 'Projected Budget' from the 'Projected Costs' to maintain a net-zero ($0) 'Projected Over/Under' value for each budget line item.
The Itemized Manual Entry setting lets you add items and amounts to create a more realistic forecast based on key job insights.
The Lump Sum Manual Entry setting lets you enter a single, fixed amount to forecast the remaining cost at completion for a specific budget code.
Note: While this setting is visible in both the Budget and Forecasting tables, it can only be configured within the Forecasting tab of the Budget tool.The Monitored Resources setting lets you add time/duration-based items that automatically draw down as time progresses throughout the project.
Add forecasting notes
Record a helpful note that documents the reasoning for the forecasted value for each budget line item. There is no limit on the number of characters you can enter on a note.
Things to Consider
Required User Permissions:
'Standard' level permissions or higher on the project's Budget tool.
Additional Information:
You can configure the 'Forecast to Complete' setting to Automatic Calculation, Itemized Manual Entry, Lump Sum Manual Entry, or Monitored Resources on a per-line-item basis.
You can add notes to each line item.
The 'Notes' entry is preserved if you decide to switch between Automatic Calculation, Itemized Manual Entry, Lump Sum Manual Entry, and Monitored Resources.
Important! When you switch from Itemized Manual Entry to Automatic Calculation, all previously added Itemized Manual Entry items will be deleted.
Net Zero Calculations:
A user with 'Admin' permissions on the Budget tool can configure the 'Forecast to Complete' column to have an automatic net-zero calculation under the Budget tool's configuration settings.
Note: This setting is applied only to new line items that you add to the budget.A lightning bolt
icon in the 'Forecast to Complete' column indicates the automatic net-zero calculation has been applied.A question mark ? icon indicates the 'Forecast to Complete' column cannot be changed. See Add a Partial Budget Line Item.
For companies using the ERP Integrations tool:
You can export a cost forecast from Procore to some integrated ERP systems. See How do I export cost forecast data from a Procore budget to ERP?
Prerequisites
Steps
Navigate to the project's Budget tool.
Click the Budget or Forecasting tab.
Locate the budget line item that you want to examine.
Select the desired calculation method:
Automatic Calculation
Follow the steps below to enable the Automatic Calculation option on a budget line item. Automatic calculation is the default setting in the project's Budget tool. This option calculates the difference between the values in the 'Projected Budget' and 'Projected Costs' columns. That difference is displayed as the value in the 'Project Over/Under' column.
To update the Forecast To Complete calculation:
In the Forecast To Complete column, select Automatic Calculation using one of these options:
Click the drop-down menu next to the amount and select Automatic Calculation.
Click the hyperlinked amount to open the configuration panel, then select Automatic Calculation from the Calculation Method drop-down menu.
(Optional) Enter any relevant information about the forecast in the Notes text box.
Note: The Notes text box is only available in the configuration panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column.(Optional) Click the bottom panel view
icon or side panel view
icon in the configuration panel to dock it to the bottom or the side of the table. Click the close
icon.
Itemized Manual Entry
To update the Forecast To Complete calculation:
In the Forecast To Complete column, select Itemized Manual Entry using one of these options:
Click the drop-down menu next to the amount and select Itemized Manual Entry to open the configuration panel.
Click the hyperlinked amount to open the configuration panel, then select Itemized Manual Entry from the Calculation Method drop-down menu.
(Optional) Click the bottom panel view
icon or side panel view
icon in the configuration panel to dock it to the bottom or the side of the table. To add line items, click Add Line Item.
For each line item, enter the following:
Description
Enter a description for the new line item.Quantity
Enter a quantity. By default, the entry is set to 1.Units
Select a unit of measure (see Which units of measure are included on Procore's master list?). The default selection is ‘ls’ (lump sum).Unit Cost
Enter the cost per unit. For example, type: 100.00. The default entry is zero (0.00).Amount
Enter the total cost associated with the line item. This is the number of units multiplied by the unit cost.
Add line items as needed.
(Optional) Enter any relevant information about the forecast in the Notes text box.
Note: The Notes text box is only available in the configuration panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column.Click the close
icon.
Lump Sum Manual Entry (Forecasting Tab)
This Lump Sum Manual Entry method should be used when you want to input a single figure to forecast the remaining cost at completion for a specific budget code in a project's budget. In the Budget tab, Procore populates the 'Lump Sum Manual Entry' amount with the 'Forecast To Complete' amount. If you want to input a different amount, you must edit the amount in the 'Forecasting' tab. To learn how to set up a forecasting view, see Create a Forecasting View.
To update the Forecast To Complete calculation:
Click the Forecasting tab.
In the Forecast To Complete column, select Lump Sum Manual Entry using one of these options:
Click the drop-down menu next to the amount and select Lump Sum Manual Entry.
Enter a lump sum amount into the text box in the cell.
Click the hyperlinked amount to open the configuration panel, then select Lump Sum Manual Entry from the Calculation Method drop-down menu.
Enter a lump sum amount in the Amount text box.
Important
Because your lump sum entry overrides the 'Forecast to Complete' amount in the budget, it is important to understand the implication that using this calculation can have on your overall budget forecast.
(Optional) Enter any relevant information about the forecast in the Notes text box.
Note: The Notes text box is only available in the configuration panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column.
(Optional) Click the bottom panel view
icon or side panel view
icon in the configuration panel to dock it to the bottom or the side of the table.
Click the close
icon.