View Daily Log Change History
Hintergrund
Change History lists all changes that have been made to the Daily Log during that day, as well as who made the modifications.
Things to Consider
Required User Permissions:
'Standard' or 'Admin' level permissions on the project's Daily Log tool.
Additional Information:
The Change History log must be enabled in the Daily Log Settings to see the change history.
Steps
Navigate to the project's Daily Log tool.
Scroll to the Change History to view the following information:
#: Dieses nicht editierbare Feld zählt die Anzahl der Einträge in einem Abschnitt (z. B. ist der erste erstellte Eintrag # 1 und der zweite Eintrag # 2).
Modification Date: This is the date and time that the recorded action was completed.
User: This indicates the user who completed the action recorded.
Description: This field details the action that was completed by the user on that date.