Manage the Project Timeline on the Project Overview
Background
From the Project Overview, you can view a card that shows key dates for your project milestones. Dates can be viewed in both timeline and list format from the Project Timeline card.
Things to Consider
Required User Permissions
To view the Project Timeline card:
'Read Only' level or higher permissions to the Project Home page.
To edit project dates from the Project Timeline card:
'Admin' level permissions to the Project level Admin tool.
Prerequisites
To add dates other than start and end dates to the Project Timeline card, your company must first create project date categories in the Company level Admin tool. See Add New Project Dates.
Steps
Navigate to the Project Overview.
Navigate to the project's Home to be redirected to the Project Overview.
Click Menu and select Project Overview.
In the 'Project Timeline' section, click Edit Timeline.
Note: If this section is missing, click the Project Overview's vertical ellipsis
and select Show Project Timeline.
Move the toggles
ON or
OFF to show or hide the dates on the Project Overview.Enter baseline and actual dates for each date that you want to include.
Click Save.