Add Quantities to a Timesheet

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.

  • Installed production quantities refers to the actual amount installed on a project by a point in time.

After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.

Dinge, die Sie beachten sollten

Prerequisites

Steps

  1. If creating a timesheet, after you have entered the timecard information, click Submit and Add Quantities.
    submit-and-add-timesheet-quantities.png
    OR
    If the timesheet has already been created, navigate to the timesheet, and click Add Quantities for the timecard entry.

  2. Enter the amount of Units Installed.

     Notes
    • You can only use cost codes that have an imported budgeted quantity associated with it.

  3. Optional: Enter any notes.

  4. Click Submit.