View a Labor Budget to Actual Report

Background

The Labor Budget to Actual Report compares hours from the Timesheets tool to your budgeted hours. It's organized by cost code, summarizing the percent of hours used, budgeted hours, and remaining hours for each cost code. It also shows the actual job-to-date hours.

Things to Consider

Things to Consider

Steps

  • View a Report from the Project's Reports Tool

  • View a Report from the Project's Timesheets Tool

View a Report from the Project's Reports Tool

  1. Navigate to the project's Reports tool.

  2. Scroll to the Project Reports section.

  3. Click Labor Budget To Actual to view the following information:

    • % Hours Used. The percent of hours used that you have imported against the hours you have entered. This is calculated, Actual Hours ÷ Budgeted Hours.

    • Budgeted Hours. The number of Budgeted Hours you imported.

    • Actual Hours. The number of hours you have entered to date in Procore's labor tracking tools (Timesheets, My Time, Company Timecard, and Daily Log).

    • Remaining Hours. The number of hours you have remaining from the hours you imported against the hours you have entered. This is calculated, Budgeted Hours - Actual Hours.

View a Report from the Project's Timesheets Tool

  1. Navigate to the project's Timesheets tool.

  2. Click Reports.

  3. Click Labor Budget To Actual to view the following information:

    • % Hours Used. The percent of hours used that you have imported against the hours you have entered. This is calculated, Actual Hours ÷ Budgeted Hours.

    • Budgeted Hours. The number of Budgeted Hours you imported.

    • Actual Hours. The number of hours you have entered to date in Procore's labor tracking tools (Timesheets, My Time, Company Timecard, and Daily Log).

    • Remaining Hours. The number of hours you have remaining from the hours you imported against the hours you have entered. This is calculated, Budgeted Hours - Actual Hours.