Create Manpower Entries

Background

The Working hours section tracks the people on site who have completed work on the project for that day. You are able to collect information on the companies on site, the number of workers, the number of hours they worked, and the cost code associated with their work.

You can configure your Working hours section so that the 'Hours' and 'Workers' values on a copied working hours entry are set to zero (0).
See Configure Advanced Settings: Site Diary.
Note: If this setting is not enabled, the copied working hours entry will include the number of hours and workers from the previous entry.

Things to Consider

  • Required User Permissions:

    • To create entries:

      • 'Standard' or 'Admin' level permissions on the project's Daily Log tool.

    • To create pending entries as a collaborator:

  • Additional Information:

Steps

  1. Navigate to the project's Daily Log tool.

  2. Scroll to the Manpower section.

  3. Fill out the following fields as appropriate:
    Tip! Certain fields in the Manpower log can be configured as required, optional, or hidden in the Company level Admin tool.


    • Note:
      This field is not enabled by default, so it may not be available on your entry. Company Admins can add the field through a configurable fieldset applied to the project.


    • Note:
      This field is not enabled by default, so it may not be available on your entry. Company Admins can add the field through a configurable fieldset applied to the project.

  4. Click Create.