View Quantities on a Timesheet (iOS)

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.

  • Installed production quantities refers to the actual amount installed on a project by a point in time.

After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

  • Required User Permissions

  • For customers using Procore Project Financials, you have the option to allow the quantities entered on a timesheet to interact with the 'Procore Labor Productivity Cost' budget view. To learn more, see Set Up the Procore Labor Productivity Cost Budget View.

  • If sub jobs are enabled on your project, the sub job associated with your 'Units Installed' entry will appear when you add quantities. See Enable Sub Jobs on Projects for WBS

  • This asset/item can be viewed or edited in offline mode provided that the asset/item was previously viewed and cached on your mobile device.

Prerequisites

Steps

  1. Navigate to the project's Timesheets tool using the Procore app on an iOS mobile device.

  2. Tap the timesheet containing the quantity you want to view.

  3. Tap View Quantities.
    timesheets-ios-view-timesheet-quantities.png