Configure default estimating settings

Background

You can configure the default profit accounting model, measurement system, currency symbol, cost code, cost types and cover pages to use in the Estimating tool across your projects.

Things to Consider

Steps

  1. Navigate to the Company level Admin tool.

  2. Under 'Tool settings', click Estimating.

  3. See the sections below for details on the setting that you can configure for projects:

    • Estimating

    • Units

    • Cost codes and types

    • Cover pages

    • Configure default views for Estimating

  4. When you are done making changes, click Save.

Estimating

  • Select your accounting model and profit structure:

    • Profit margin: sales minus the cost of goods sold. See What is the difference between markup and margin?

      • To use Minimum margin profit, click the toggle to the ON position.

      • Enter the 'Minimum material margin percentage' and 'Minimum labour margin percentage.

         Note

        If a 'Minimum Margin Profit' is set, users creating estimates cannot set a markup or margin in an estimate that is lower than the value configured here, unless they have 'admin' level permissions to the tool.

    • Profit markup: The amount by which the cost is increased on a product to arrive at the selling price. See What is the difference between markup and margin?

      • To use Minimum markup profit, click the toggle Icon Toggle On to the ON position.

      • Enter the Minimum markup margin percentage and Minimum labour markup percentage

         Note

        If a 'Minimum Markup Profit' is set, users creating estimates cannot set a markup or margin in an estimate that is lower than the value configured here, unless they have 'admin' level permissions to the tool.

    • Unit cost pricing: When using unit cost pricing for labour, labour is set at a flat rate. See What is the difference between individual labour rates and unit cost pricing for labour?

      • If you want to enable unit cost pricing for labour, click the toggle Icon Toggle Onto the ON position.

         Note
        • When unit cost pricing is enabled, labour is set at a flat rate. It calculates labour as quantity x labour cost.

        • If disabled, labour is set as a Labour rate. When using labour rates, you set the labour rate as the cost per hour/minute and then indicate the quantity of required minutes or hours. You can also include a 'difficulty' multiplier that indicates how many people are needed to perform the work.

Units

Default measurement system

  • Select Imperial or metric as the default measurement system for all projects.
    Note: The measurement system can be changed for an individual project if needed. See Configure settings: Estimating.

Currency symbol

  • If you want to change the currency symbol shown on estimates across all projects, type the symbol in the field (for example, £, € or AUD).
    Note: The symbol cannot be more than 3 characters long.

Cost codes and types

 Notes
  • These setting are applied when estimates are sent to your Budget and are set in either the Estimating setting in the company's admin tool or when configuring setting in the company's Tender Board tool. If the settings are updated in one tool, they will be updated for both tools.

  • It is recommended that you break down cost code and cost types further for standard price adjustments such as Profit, Overhead, Discount, Tax and Others (such as Bonding). Configuring cost code and cost types for one or more of these categories will help to ensure cost are appropriately outlined on your project's Budget.

  • If needed, these settings can be overridden before the estimate is sent to a project's Budget.

  • If you are integrated with QuickBooks®, click the toggle Icon Toggle On to the ON position to Use QuickBooks® Friendly Codes Only.
    This setting is only intended for projects integrated with QuickBooks®. Enabling this setting will remove cost types and automatically set all cost code to 'Other' so that estimates can be pushed to the Budget in Procore. Note: This setting is not retroactive, so any estimates using other cost types will push to the Budget with the previously assigned cost types. You will need to create a new estimate to have the cost code on the Budget without custom cost types.

  • Select what you want to send to the budget:

    • Send cost only

    • Send entire estimate including additional adjustments

      • For standard price adjustments such as profit, overhead, discount, taxes and others:

        • Click the toggle Icon Toggle Onto the ON position to map each to individual cost types and cost code.
          OR

        • Click the toggle Icon Toggle Off to the OFF position to apply the same setting to all.

        • Select how you want to distribute below the line adjustments to your budget:

          • Spread across estimate item.

          • Summarise into specific budget code.

            • Click Select or the current selection to configure the cost code and cost type for each.

            • Click Save Changes.

Cover pages

You can choose to add PDF cover and appendix pages that can be used in proposal exports.

  • To add cover pages to use for estimates:

    1. Click Add cover.

    2. Select a file to upload.

    3. Click Upload to add the file.

  • To delete a cover page:

    1. Click the trash recycle bin Icon Delete Esticom icon next to the file.

    2. Click Delete to confirm the deletion.

Configure default views

See Configure default views for estimating

See Also

Loading related articles...