Assign assets to projects from the Company Assets tool
Background
Company level assets can be assigned to projects so they can be managed, tracked and used within project workflows. Assets can be assigned individually or in bulk.
Things to Consider
Each asset can be assigned to one project at a time.
You can bulk assign up to 500 asset to a project.
Related items, such as inspections and submittals, are retained when assets move between projects.
When an asset is moved to a project, parent and sub asset are also added to the same project to keep the hierarchy intact.
Steps
Assign inline
Bulk assign
Assign inline
Navigate to the company's asset tool.
Locate the asset you want to assign.
Under the 'Projects' column, click the project field for that asset.
Select a project.
Optional: Add a note.
Click Assign or Move to assign the asset to the project.
Bulk assign
Navigate to the company's asset tool.
Mark the tickbox for each asset you want to assign.
Click Assign to project.
Select the project from the project.
Optional: Add a note.
Click Assign to assign the asset to projects.