Create a funding variation from a change event
Background
If the change event tool is enabled on your project, your project's variation tier configuration setting (see What are the different variation tier settings in Project Financials?) determines the number of steps leading up to creating a funding variation.
If the 1-tier variation setting is enabled, you will simply use the steps below to create a funding variation from a change event.
If the 2-tier variation setting is enabled, you will complete the first step in the change management process, Create a potential variation for a funding, before using the steps below.
If the 3-tier variation setting is enabled, you will complete the first two steps in the change management process, Create a potential variation for a funding and Create a variation request, before using the steps below.
Are you inviting your downstream collaborators to submit tenders for goods and services using formal RFQs?
If your project team has opted to use Procore's request for quote process (see Create RFQs from a change event), you do NOT have to wait until the RFQ process is complete to create your funding variation. However, after invited collaborators respond to RFQs and its status is set to 'Pending final approval,' Procore does automatically update the variation's bill of quantities (BOQ) with the appropriate amounts from the RFQ.
To learn more about how the RFQ process affects funding variations, see What are the different RFQ status and how do they affect cost and variation amounts?
Are you using the Revenue ROM function?
If your project team has opted to use the Revenue ROM function, the BOQ on your funding variation is also automatically updated. If you have hidden the Revenue ROM function, any automatic updates depend upon the scope of the change event:
When change events are 'In Scope' or 'TBD', the variation's bill of quantities is automatically updated with a £0 value.
When change events are 'Out of scope', the variation's bill of quantities is automatically updated using the data in the RFQ. This update occurs when the RFQ status is set to 'Pending final approval.'
When change events are not in one of the above statuses, the variation's bill of quantities is automatically updated using the 'cost ROM'.