Accept or reject a MCV for export to enterprise resource planning

Enterprise resource planning documentation

Each Procore-built enterprise resource planning integration offers its own unique feature set. Your integration might not support the action described on this page.

To learn about your integration and its supported features, see Which ERP integrations are supported by Procore?

Background

After a user sends an MCV to the ERP integration tool for accounting acceptance, an accounting approver has the option to 'Accept' or 'Reject' the MCV for export to the ERP system.

 Note

If there is at least one MCV in the ERP Integrations tool that's awaiting accounting acceptance, Procore sends an automated email notification to the people at your company who are designated as ERP accounting approver(s). Accounting approvers will receive the email once per day with the subject line 'ERP integrations daily summary' until their response is submitted.

Things to Consider

Steps

  • Review an MCV

  • Accept an MCV

  • Reject an MCV

Review an MCV

  1. Navigate to the company's enterprise resource planning integration tool.

  2. Click main contract variations.

  3. Under Filter main contract variations by, click Ready to export.
    Note: All of the MCVs in this page were sent to the ERP integrations tool for accounting acceptance.

  4. In the project's table, locate the desired MCV. Then choose one of these methods to review it:

    • To open the project's Main Contracts tool, click the Main Contracts hyperlink.

    • To open a PDF copy of the variation, click the PDF icon on the left side of the table.

    • To open the MCV in the main contract tool, click the MCV number (#).

  5. Return to the Ready to export tab. Then continue with one of the following:

    • ​Accept an MCV

    • Reject an MCV

Accept an MCV​

  1. Locate the desired MCV in the main contract variations list.

  2. Click Accept.

  3. Enter the transaction date or leave as today's date.

  4. Click Export to ERP .
    This exports the MCV to your ERP system.
    Set Transaction Date For Pcco Export To Integration

  5. (Optional) To verify that the sync was successful, log into your ERP system and verify that your data appears as expected.

Reject an MCV

  1. Locate the desired MCV in the main contract variations list.

  2. Choose Reject.Reject Pcco Export To Integration

  3. Enter an optional comment and click Reject.

The following events occur:

  • The system removes the MCV from the enterprise resource planning integration tool and returns it to an editable state in the project's main contract tool.

  • The system sends an automated 'ERP MCV rejection notification' to the user who created the MCV. This alerts the user of the 'Reject' response.

See Also