Edit a commitment synced with ERP

Enterprise resource planning documentation

Each Procore-built enterprise resource planning integration offers its own unique feature set. Your integration might not support the action described on this page.

To learn about your integration and its supported features, see Which ERP integrations are supported by Procore?

Background

In some cases, you might need to edit a commitment that has been synced with your ERP system instead of creating a variation. Commitments can't be edited while in the 'Approved' status and most commitment fields can't be edited while the contract is synced with ERP. Before you can edit a commitment, you may need to take steps like changing the status or unlinking the commitment, before you can make the desired changes.

Things to Consider

  • Required User Permissions:

    • 'admin' level permission on the project's commitment tool.
      OR

    • 'Standard' or 'Read Only' level permission on the project's commitment tool with the following granular permission:

      • 'Update purchase order contract' and/or 'Update work order contract'

Steps

  1. Complete any prerequisites required for your specific ERP integration.

  2. Navigate to the project's Commitments tool.

  3. Locate the desired commitment in the list of commitments.

  4. Click Edit.

  5. Make changes as needed.

  6. Click Save.

  7. Re-send the update commitment to your enterprise resource planning integration for accounting acceptance.