Re-import a main contract from an integrated ERP system into Procore

Enterprise resource planning documentation

Each Procore-built enterprise resource planning integration offers its own unique feature set. Your integration might not support the action described on this page.

To learn about your integration and its supported features, see Which ERP integrations are supported by Procore?

Background

Some ERP integrations allow you to import a main contract from your integrated ERP system into the Main Contracts tool in a Procore project. After your contract is successfully imported, you can then continue to modify and update it in Procore. If someone in your organisation changes the main contract in your ERP system, you will need to manually sync and re-import your main contract into Procore.

Things to Consider

  • Required User Permissions:

    • To perform this action, a user must have all of the following permissions and privileges:

      • 'Admin' level permission on the ERP Integrations tool.

      • 'Admin' level permission on the Project level main contract tool.

      • The person's account must be granted the 'Can push to accounting' privilege in the company Directory. See Grant accounting approver privileges.

      • The user's permissions in the company Directory must have the 'Can Import?' tickbox enabled for the main contract item type under the ERP permissions section.

  • Prerequisites:

    • The Company level ERP Integrations tool has been configured to work with your company's Procore account.

    • The main contract that you want to sync with Procore has been updated in your integrated ERP system. For example, you've added one or more line item(s) or changed existing line item(s).

  • Additional information:
    You will not be able to re-import a main contract when:

    • The main contract is in an unapproved state.

    • The main contract does not belong to a synced job.

    • The main contract has inadvertently been added to two projects in your company's Procore account.

Steps

  1. Navigate to the Company level ERP Integrations tool.

  2. Click the main contract tab.

  3. Click the Synced option in the right sidebar.

  4. Locate the desired project's Budget in the enterprise resource planning main contracts ready to be imported list.

  5. Click Re-Import.