Remove a variation from a main contract
Background
Before you can remove a main contract variation (MCV) from Procore (as described in Delete a main contract variation), you must use the steps below to remove any PVs or VRs linked to that MCV.
Things to Consider
Required User Permissions:
'Admin' level permission on the project's main contract tool.
Prerequisites
Before changing the status of multiple MCVs from 'Approved' to another status, be aware that you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002 and 003), you will need to unapproved them in reverse order (003, 002, 001).
If any variations have been added to your project's payment applications, you must delete those payment applications before you can use the steps below.
Steps
Navigate to the variations tab
Change the status of the main contract variations from 'Approved'
Unlink potential variations and variation requests
Delete the potential variations and variation requests
Navigate to the variations tab
Navigate to the project's main contract tool.
Locate the main contract to work with. Then click its Number link.
Click the Variations tab. Depending on the number of variation tiers configured for the tool, the following tables appears in the tab:
Main contract variations
Potential variations
Variation requests
Change the status of the main contract variations from 'Approved'
Before changing the status of multiple MCVs from 'Approved' to another status, be aware that you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002 and 003), you will need to remove the 'Approved' status in reverse order (003, 002, 001).
In the main contract variations table, locate the 'Approved' MCVs.
Click View to open the MCV.
Click Edit.
In the status drop-down list, change the status from 'Approved' to a different status.
Click Save.
Unlink the potential variations and variation requests
Scroll to the Potential variations included in this MCV section.
Locate the VR or PV to work with. Then click View.
Click Edit.
Scroll to the main contract variation drop-down list as shown below.
Choose None.

In the potential variations list, remove all of the existing PVs from the list:

Click Save.
Delete the potential variations and variation requests
Return to the variations tab.
Locate the PV or VR to remove.
Click the red (X) next to each PV or VR to remove.

In the confirmation dialog box that appears, click OK to confirm the removal action for the selected PV or VR.