Update the percent complete for a programme task (Android)

Things to Consider

  • Required User Permissions:

    • You need one of the following:

      • 'Admin' level permission on the Project level programme tool.

      • 'Read Only' or 'Standard' level permissions with the 'Update task completion percentages' granular permission enabled on the permission template.

  • Additional Information:

Prerequisites

Steps

  1. Navigate to the project's Programme tool using an Android mobile device.

  2. Tap the programme task you want to update.

  3. Tap Edit.
    Edit Schedule Item Android
    Note: Percent complete cannot be updated for summary programme tasks or milestones.

  4. Enter the current Percent complete for the task and tap Done.
    Save Scheduled Item Android
    Note: You can enter a numeric value from 0 to 100. The value you enter must be a whole number.

  5. Tap Save.

  6. The programme task on the mobile device update to show the amount you entered for Percent Complete.
    Note: These changes are also shown in the Programme tool on the web application.