Use bulk actions > Edit in the submittal tool

Background

Use the bulk actions > Edit option when you want to apply the same edits on multiple submittal.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permission to the project's submittal tool.

  • Supported views:

    • The bulk actions menu is supported in the Submittals tool's items, packages, spec sections and Ball in Court views. See Switch between submittal views.

    • The bulk actions menu is dimmed and unavailable in the recycle bin view.

  • Additional Information:

Steps

  1. Navigate to the project's submittal tool.

  2. Locate the submittals to modify in the items, packages, specification sections or Ball in Court tabs. Then:

    • To select all of the submittal in the list, mark the tickbox at the top of the left column.
      OR

    • To select one or more of the submittal in the list, mark the tickbox to the left of each desired submittal.

  3. Choose Bulk actions > Edit .
    Note: The bulk actions menu is NOT available in the recycle bin. See Perform bulk actions on submittals.

  4. Choose from these editing options:
    (Note: Editing options in your project's submittal tool can vary if your company has configured custom fields and configurable fieldsets.)

    Submittals Bulk Edit Page

    • Specification section. Denotes the corresponding section from the project's specifications. See Where do the selections in the 'Specification sections' drop-down list in the submittal tool come from?

    • Submittal manager. The name of the submittal manager. This is the person who is responsible for overseeing the submittal throughout its lifecycle in Procore. Each submittal can have a different submittal manager or your project team can configure a 'default submittal manager' for all of your submittals. See What is the 'submittal manager' role?

    • Responsible contractor. The company that is responsible for completing the work specified on the submittal.
      Note: Users can only be added to the 'Received From' field if their Procore Directory record is associated to the company listed as the 'responsible contractor' on the submittal.

    • Cost code. Select a cost code to associate with the selected submittal.

    • Received from. The contact for the responsible contractor who provided the submittal information to the project team.
      Note: Users can only be added to the 'Received From' field if their Procore Directory record is associated to the company listed as the 'responsible contractor' on the submittal. To add a user to the 'Received From' field who is not associated with a submittal's current 'responsible contractor', first select the desired user's company in the 'responsible contractor' menu. Then you are able to select the user's name in the 'Received from' menu.

    • Add to distribution list. Add one (1) or more users and/or distribution groups to selected submittals’ distribution lists.

    • Remove from distribution list. Remove one (1) or more users and/or distribution groups from selected submittals’ distribution lists.

    • Private. Select Yes to make the selected submittals private. Otherwise, choose No.

    • Status. The current status of the submittal. Only a user with 'admin' level permission to the submittal tool can change a submittal's status. See What are the default submittal status in Procore? and What is a 'draft' submittal?

    • Type. The information type associated with the submittal. The default type selections in Procore include: Document, Plans, Prints, Product Information, product manual, Sample, Shop Drawing and Other. See Create custom submittal types.

    • Location. The location at the job site for the submittal. This can be an existing location from the location list or a tiered location. See Add tiered locations to a project.

    • Sub job. If sub jobs are enabled on your project, select one to associate it with the selected submittals. See What's the difference between a job, a parent job and a sub job?

    • Lead time. The expected number of calendar days that will be required for the material/services for the submittal to arrive.

    • Submit by. Select the date by which a contractor/subcontractor must submit all relevant documentation (i.e., documents, drawings, manuals, plans and so on) for the submittal to the project's design team for review.

    • Received date. The date that the submittal information was received from the contractor/subcontractor responsible for the performing work associated with the submittal.

    • Issue date. The date the contractor/subcontractor submitted the submittal item (i.e., documents, plans and so on) to your project team for the review process.

    • Required on-site date. The date by which materials related to the work detailed on the submittal must be delivered and available at the construction site.

  5. Click Update.
    A GREEN banner appears to confirm the total number of submittal successfully edited. A RED banner appears when edits are not successfully saved.