What is sliding scale retention?

 Note

flag-australia.png The sliding scale retention feature was designed for Procore users in Australia and New Zealand—where it is an industry-wide best practice and legally regulated standard—to assure contractors and subcontractors meet all of the job's contractual obligations. However, this feature is available to Procore Project Financials customers in all countries.

Using Owner or Specialty Contractor Terminology?

Procore can be configured to use terminology specific to General Contractors, Owners, or Specialty Contractors. Learn how to apply the dictionary options.

  • To learn the differences: Show/Hide

    • This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials.

      Entrepreneurs généraux
      Anglais (États-Unis) - Par défaut

      Propriétaires
      Anglais (Terminologie du propriétaire V2)

      Entrepreneurs spécialisés
      Anglais (terminologie des entrepreneurs spécialisés)

      Facturation

      Facturation

      Facturations proportionnelles

      Propriétaire

      Financement

      Propriétaire

      Propriétaire/Client

      Propriétaire/Client

      GC/Client (en anglais seulement)

      Ordre de changement au contrat principal

      Ordre de changement au financement

      ordre de changement de contrat de client

      Contrats principaux

      Financement

      Contrats clients

      Chiffre d’affaires

      Financement

      Chiffre d’affaires

      Contrat de sous-traitance

      Contrat

      Contrat de sous-traitance

      Sous-traitant

      Entrepreneur

      Sous-traitant

      Ventilation des coûts des sous-traitants (VDCST)

      Ventilation des coûts de l’entrepreneur (CSOV)

      Ventilation des coûts des sous-traitants (VDCST)

      About These Dictionaries
      • Default Setting: The 'General Contractor' dictionary is enabled by default for all accounts.

      • Availability: These alternate dictionaries in italics are available in US English only.

      How to Switch Your Dictionary

      To change your company's terminology to the Owner or Specialty Contractor dictionary, contact your company's . They will work with your Procore Point of Contact to make the change.

Answer

Sliding scale retention refers to the portion of a contract amount due that is withheld from a contracted party (the party doing the work) by the contracting party (the party paying for the work). The amounts withheld are based on a set of variable standards defined in the contract's scope of work. It is an industry-wide best practice in Australia, as well as legally regulated, to assure contractors and subcontractors meet all of the job's contractual obligations.

Example: Applying Sliding Scale Retention in Procore

Although the terms of the retention on your construction project's contracts will vary from contract to contract, below is an example to show how sliding scale retention is designed to work:

  1. Let's assume you are a general contractor who has executed a $400,000.00 subcontract with a heavy equipment operator.

  2. During the course of the project, you plan to make progress payments to the subcontractor. Per your agreement, let's assume you have an industry-standard contract that obliges you to deduct 10% of the amount due on each subcontractor invoice until 5% ($20,000.00) of the original subcontract's value ($400,000.00) is held back.

  3. When 100% of the work on the subcontract's Schedule of Values (SOV) is complete, your agreement obliges you to release the first portion of the amount held back. In this example, you would want to release the first 2.5% ($10,000.00) of the original subcontract's original value ($400,000.00).

  4. In six (6) or twelve (12) months after the first portion of the retention amount was released, your subcontract's terms require you to release the remaining 2.5% ($10,000.00) withheld from the subcontractor.

See Also

Loading related articles...