Create a Prime PCO from a Change Event

Background

If your company has configured your project to use a two (2) tier change order structure, the change event process requires you to create a potential change order. Then, you will create the PCCO from the Prime Contract tool. When you create a PCO, the Schedule of Values (SOV) will populate with the Latest Price values.

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Change Events tool.

  2. In the table, mark the checkboxes for one (1) or more change event line item(s) to include in the new potential change order.

    Note icon Note

    Procore creates the potential change order's Schedule of Values (SOV) using the selected change event line item(s).

  3. Click the Bulk Actions menu and choose the Create Prime PCO option. Then choose the appropriate contract option from the sub menu.
    create-prime-pco-from-change-events.png

  4. In the 'New Potential Change Order' page, complete the following data entry:

    • Tip icon Tip

      How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.

    • Note icon Notes
      • Procore automatically assigns the item a new number in sequential order. For example; 001, 002, 003, and so on.

      • To use a custom numbering scheme, enter any set of alphanumeric characters. Procore automatically assigns new numbers in sequential order using your custom scheme.

    • Note icon Note

      If the Request for Quote (RFQ) feature is turned ON, you can configure the Change Events tool to include any attachments added to a reviewer's RFQ response. For instructions, see Configure Settings: Change Events.

  5. Click Create.

    Note icon Notes
    • The Associated Line Item drop-down list only appears if your company's Procore account is integrated with an integrated ERP system and the Prime Contracts tool is active on the project.

    • When adding line items to the change order's schedule of values, you must select an Associated Line Item for each new line item. You can designate one (1) associated line item or use the same associated line item for multiple line items. Choosing to create a new line item to associate will automatically create a new zero (0) dollar line item on the contract's original SOV.