Ce site Web n’est pas encore entièrement disponible dans votre région.
La seule page opérationnelle du site de support V2 dans votre région préférée est la page de la bibliothèque de vidéos. Le site Web complet sera bientôt lancé.
Vous recherchez d'autres contenus? Retournez au site de support V1.
In Procore, a Purchase Order (PO) is a formal financial commitment documenting the specific types, quantities, and agreed-upon prices for products or services. These orders are an essential part of the procurement process. A buyer (for example, a General Contractor) creates and issues a PO to a seller (for example, a Subcontractor) to cover the cost of a contract. Once the seller accepts the PO, it represents an agreement between both parties.
and
A Subcontract is a legal agreement where a party on a prime contract engages a third-party (the subcontractor) to perform all or part of the work defined in the prime contract.
are called commitments. A commitment is a contractual agreement between a buyer (for example, a project owner, a general contractor, or a specialty contractor) and a seller (for example, a contractor, a subcontractor, or a vendor). The seller is responsible for completing project work or fulfilling an order for the buyer. When you need to alter the terms of the original agreement, you can create a commitment change order.
Important
When the Change Events tool is enabled on a project
The process that you will use to create a commitment change order in Procore depends upon a few factors. First, if the Change Events tool is disabled on the project, you will use one of the processes below. Also, keep in mind that the number of steps required to create a commitment change order is dependent upon the change order tier setting that is configured on the project's Commitments tool. See Configure the Number of Commitment Change Order Tiers:
1-Tier configuration:
Create a commitment change order as described below.
2-Tier configuration
Create a commitment potential change order
Create a commitment change order
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Commitments tool
'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow Standard Level Users to Create CCOs' configuration must be selected.
Additional Information:
If the Change Events tool is disabled on the project:
If your company is using the ERP Integrations tool: Show/Hide
Additional requirements, considerations, and limitations vary depending on the ERP system your company's account is integrated with. Most ERP systems have limitations on the number of characters that can be used for a commitment's title. See Things to Know About your ERP Integration for details.
If you have created a purchase order or a subcontract and need to alter the terms of that item, use the steps below to create a commitment change order.
Navigate to the project's Commitments tool.
Under Contracts, locate the commitment. Then click Edit.
Click Create Commitment CO.
Notes
If the Change Events tool is enabled on your project, the Create Commitment CO button is not available. Follow these steps instead:
Sign with DocuSign® If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.
Tip
How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.
Number This field automatically populates based on the number of change orders already created. By default, the number will automatically increment by one.
Displays the change order's revision number. When a change order is first created, its revision number is zero. A change order could have multiple revisions because of feedback from a reviewer/approver.
Date Created Automatically populates with the date that you create the commitment change order. The date cannot be changed.
Created By Automatically populates with the name of the user who is creating the change order.
Contract Company Automatically populates with the name of the subcontractor or vendor listed on the subcontract. This field is only available for subcontracts.
Contract Automatically populates with the name of the contract for which the change order is being created. This field is only available for subcontracts.
Title Enter a name for the change order. The maximum character limit is 255 characters.
Private Mark this checkbox to make the change order visible only to users with 'Admin' level permissions on the Commitments tool.
Change Reason Select one of these reasons for the potential change order: Client Request, Design Development, Allowance, Existing Condition, or Backcharge. To learn how to configure change reasons, see Set Default Change Management Configurations.
Accounting Method This field inherits the accounting method that was specified in the contract.
Due Date Select a due date for when the change order must be approved by.
Invoiced Date Select the date when the change order was invoiced.
Designated Reviewer Select the Procore project user at your organization who will be responsible for approving or rejecting this change order later. See Approve or Reject Commitment Change Orders.
Important
The 'Designated Reviewer' can submit an approve or reject response only when a change order is in the Pending - In Review status.
To send an email notification to the 'Designated Reviewer' to notify that person that a change order is awaiting their response, you have these options:
The pending change order will also be listed in the 'My Open Items' area in the project's Home page. The user can check this page at any time.
After the 'Designated Reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'Designated Reviewer' field) shows the date/time stamp of that users response. The 'Reviewer' field is only visible to the 'Designated Reviewer.'
Request Received From Select a user from the project's directory who you are submitting the change order on the behalf of.
Description Enter a detailed description of the change order.
Notes
If you are exporting the change order to Sage 300 CRE® and Integration by Procore, entries exceeding one thousand (1000) characters will be truncated during the export.
If you will be exporting the change order to a different integrated ERP system, you can to enter an unlimited number of characters in Procore.
Schedule Impact If known, you can provide an estimate of the number of additional days that would potentially be added to the current project schedule if the change order were approved.
In Beta
Note to users participating in the 'Subcontractor Estimated Completion' limited release beta program. When a user places a change order in the 'Approved' status and it includes a value in 'Schedule Impact' field of the change order, Procore automatically updates the 'Estimated Completion Date' field in the commitment contract by the number of days entered.
Location Use the location drop-down menu to select a location the [item] impacts. Either select from the predefined locations, or add a multi-tiered location. See Add a Multi-tiered Location to an Item. This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier.
Reference Reference any other tools, materials or documents that are related to the change order.
Executed Mark this check box if the change order has already been executed.
Field Change Mark this check box if the change order requires a field change.
Paid in Full Mark this check box if the cost is already covered in the budget.
Attachments Select and add any relevant documents.
Click Create or Create & Email to send the change order to any users listed as 'Reviewers'.
Add a Schedule of Values (SOV) to the Change Order
If there are costs associated with the change order, add line items to the change order's Schedule of Values (SOV).
Click the Schedule of Values tab.
Click Edit.
Click Add Line.
Prime Contract Line Item Select a line item from the drop-down list. If there is no line item that fits, select Not Budgeted.
Change Event Line Item Select a change event line item from the drop-down list.
Description Type a description for the new change order.
Cost Amount Enter an amount in the box.
Optional:Tax Codes If you are using tax codes with this project, select a tax code to use for the line item.
Tip
Don't see the Tax Codes field? This field only appears when the tax codes feature is enabled on the Procore project. See How can I use tax codes on a project?
Click Add
Repeat these steps for each line item.
Click Save.
Note
For Companies That Have Enabled the ERP Integrations Tool
After the commitment change order is placed into the 'Approved' status in the Commitments tool, project managers will typically send the change order to the ERP Integrations tool where it must be accepted by an accounting approver for export to the integrated ERP system. For instructions, see Send a CCO to ERP Integrations for Accounting Acceptance.