Add Scheduled Work Log Entries (Android)

Éléments à prendre en compte

  • Required User Permissions:

  • Additional Information:

    • Entries made by collaborators are marked as 'pending' until approved by an administrator.

    • There are additional workforce labor categories that can be added to the Daily Construction Report in the Daily Log: (e.g. Women, Veteran, Minority, First-Year Apprentice, Local (City), and Local (County)).
      In order to track hours for these additional workforce labor types, these fields must first be configured in the Daily Log section of the Company Admin tool, and then applied to one or more projects.

      See How do I enable additional workforce labor types for the Daily Log?
      Note: After configured and applied, a 'Workforce Hours' column will be available with a link to 'Add Hours' link will appear in the Daily Construction Report section.

  • Vous pouvez configurer les items créés à l’aide de l’icône de création icon-plus-quick-create-mobile2.png rapide, voir Configurer les paramètres de création rapide.

  • Cette action peut être effectuée hors ligne. Les tâches effectuées hors ligne sont synchronisées avec Procore une fois qu’une connexion réseau est rétablie.

Steps

  1. Open the Procore app on an Android mobile device and select a project.
    Note: This loads the Tools screen for the project.

  2. Tap the quick createicon-plus-quick-create-mobile2.pngicon and select Scheduled Work.
    OR
    Tap the Daily Log tool. Tap the createicon-plus-quick-create-mobile2.pngicon, then tap Work Entry.

  3. Tap into the following fields to enter the relevant information:

  4. Tap Save.

 Tip
  1. Click Fix Errors to go to the first empty field, if the required fields are empty.

  2. Click Next Field or Previous Field to view other empty required fields.
    After the required fields have been entered, you will be able to create or save the form.

See Also