Update a Shipment
In BetaThis feature is currently in beta for select Procore customers.
This feature is currently in beta for select Procore customers.
Things to Consider
To edit a shipment, the 'Shipment Document' status must be set to 'Pending'.
To create a receipt, the 'Shipment Document' status must be set to 'Release'.
Steps
Navigate to the project's Materials tool.
Click the Control tab.
Click the Shipments sub tab.
Click the shipment number.
Edit the following information:
Destination and Vendor
1. In the 'Properties' menu, click the edit
icon.2. Click the value for the 'Destination' field and enter the destination.3. Click the value for the 'Vendor' field and enter the vendor.
Status
1. Click the status next to 'Document Status'.* Select Release when the items have been shipped and are in transit.* Select Hold to put it back into a 'Pending' status.
Containers1. Follow steps to Add Materials to a Container.
Line items
Note: By default, the quantities on the shipments will match the quantities for each line item on the order.1. Click the quantity field and enter the quantity.
2. Update the estimated delivery date.
Attachments1. Upload Attachments to Materials