Add Quantities to a Timesheet (iOS)

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.

  • Installed production quantities refers to the actual amount installed on a project by a point in time.

After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.

Éléments à prendre en compte

Conditions préalables

Steps

After you fill out your timesheet, perform the following actions before you submit:

  1. Tap Submit.

  2. Tap Submit and Add Quantities.
    2018-07-10_10-21-27.png

  3. If prompted, click Add Line.

  4. Tap Units Installed Today and enter the quantity installed.

  5. Optional: Enter any notes.

  6. Click Submit.