What custom segments should we create for our company's Work Breakdown Structure?

バックグラウンド

Procore の 作業分解構成図 (WBS) では、セグメントは、WBS の構成要素とそれらの構成要素間の関係を説明するために使用される概念です。セグメントとそのセグメントが Procore でどのように機能するかについて詳しくは、「 セグメントとセグメント項目とは何ですか?」を参照してください。

Answer

At a minimum, your WBS in Procore must contain two (2) segments: Cost Code and Cost Type. Some companies also choose to add the optional Sub Job segment. If you want to be able to record financial line items with more granularity and generate reports for your project financials with more flexible grouping and sorting options, the table provides you with some common examples of how Procore customers can leverage custom segments in Procore's WBS.

 Note

An effective WBS that meets the needs of your business always requires input from your company's stakeholders. When considering which segments to create, be sure to include your stakeholders in your discovery and planning process.

General Contractor

Example Custom Segments

Phase

Task

Building

Area

Pay Item

Owner

Example Custom Segments

Phase

Year

Building

Location 1

Facility

Contractor

Funding Source

Cost Center

Specialty Contractor

Example Custom Segments

Location

Phase

General Overhead

Project Overhead

1 If you create a custom segment named 'Location', be sure to inform your users that it is a distinct segment for your company's Work Breakdown Structure. Custom segments are not integrated with the 'Locations' field, which is associated with the multi-tiered locations feature in Procore. See What are multi-tiered locations?