View and Filter the Change History of the Budget

Background

You can view a detailed record of every change made to a project's budget. This history shows what was changed, who made the change, and when it occurred. This helps you track updates and maintain a complete audit trail for the budget.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the project's Budget tool.

  • Additional Information:

    • Items in the change history cannot be deleted.

Steps

  1. Navigate to the project's Budget tool.

  2. Click the Change History tab.
    This opens the Change History page.


    budget-change-history.png


  3. (Optional) Choose one of these options to apply filters to the data table:

    • Select an item from the Sub Job, Cost Code, or Cost Type drop-down list above the table.
      OR

    • Click Filters. Then choose the filters to apply from the lists in the side panel.