Create a Commitment Potential Change Order from a Change Event
Background
Your project's change order tier configuration settings determines if you need to create a potential change order for a commitment:
1-Tier Change Orders. You don't need to create a potential change order and can skip the Steps below. Instead, you simply create a commitment change order.
2-Tier Change Orders. First, create a Change Event. Then, use the Steps below to create a potential change order for your commitment from the change event.
Note
If your project is using the optional Request for Quote (RFQ) feature in the Change Events tool, you can create the potential change order either before or after the RFQ has a response. However, if you wait until the RFQ has been reviewed and placed into the Pending Final Approval status, Procore will automatically populate the potential change order's Schedule of Values (SOV) with the RFQ amount.
Things to Consider
Required User Permissions:
You need one of the following:
'Admin' level permissions on the project's Commitments tool.
'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow Standard Level Users to Create PCOs' configuration must be selected.
Requirements:
The Change Events tool must be enabled on the project.
The Commitments tool must be configured for two-tier change orders.
Additional Information:
After you create a change event, you have the option to create a RFQ.
On commitments, potential change orders can be transitioned into change orders.
Place a checkmark next to the change event line items to add to the potential change order.
Notes
To show only line items for a specific vendor, click Add Filter and then choose Vendor from the drop-down list.
You can select multiple line items from multiple change events.
Click Bulk Actions and choose one of these options:
Create a Commitment PCO > Contracts with Matching Cost Codes If there are contracts with cost codes that match the change event line items you select, they will appear here for your selection.
Create a Commitment PCO > Contracts All other approved contracts will appear here for your selection. Note: If an option is grayed out and dimmed, hover your mouse cursor over the tooltip to learn why.
Under General Information in the New Potential Change Order page, enter the following information:
Number Procore automatically assigns the next available number to the potential change order. By default numbers are assigned as 001, 002, 002, and so on.
Tip
You can manually override this by typing over the number if desired. For example, you might want your numbering scheme to use three (3) leading zeros instead of two (2): 0001
If you override the default number, Procore automatically increments the numbering using your new entry and format.
Date Created This field logs the date and time the potential change order was created.
Revision When you first create a potential change order, the revision number is zero. Note: Later in the project, a potential change order might have several revisions because of feedback from a reviewer/approver.
Created By This field automatically displays the name of the user creating the potential change order.
Contract Company This field automatically populates with the name of the subcontractor or vendor listed on the subcontract. Note: This field is only visible if the potential change order is for a subcontract.
Contract This field automatically populates with the name of the contract for which the potential change order is being created. Note: This field is only visible if the potential change order is for a subcontract.
Title Enter a title name for the potential change order that describes what the change order is for.
Note
Before exporting the potential change order to an
In Procore, the term integrated ERP System, is used to refer to Enterprise Resource Planning (ERP) software applications that can be configured to exchange data between Procore and a supported application using the Company level ERP Integrations tool. See Which ERP integrations are supported by Procore?
, keep in mind that there may be character limitations.
Commitment Change Order
Status Select the current state of the potential change order. Procore's default status is Pending-In Review.
Field Order
Change Order Request
None. This is the default setting. You can link the potential change order to a change order request at a later time.
Add to Existing. Choose this option. Then select an existing change order request from the drop-down list.
Create New. Choose this option to create a new change order request. Note: You also have the option to create a new commitment change order by placing a checkmark in the Also Create New Commitment Change Order box.
Change Reason The change reason field will populate with the change reason you selected in the change event; however, you can edit as necessary. Select one of these reasons for the potential change order: Client Request, Design Development, Allowance, Existing Condition, or Backcharge.
Private Check this box so only you and users with 'Admin' level access on change order can view this change order.
Description Enter a detailed description of the commitment potential change order. Note: If you will be exporting the commitment potential change order to an
In Procore, the term integrated ERP System, is used to refer to Enterprise Resource Planning (ERP) software applications that can be configured to exchange data between Procore and a supported application using the Company level ERP Integrations tool. See Which ERP integrations are supported by Procore?
there may be character limitations imposed by the third-party system.
Request Received From Select a user from the project's directory who you are submitting the commitment potential change order on the behalf of.
Location Use the location drop-down menu to select a location the [item] impacts. Either select from the predefined locations or see How do I add a multi-tiered location to an item?. This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier.
ScheduleImpact If known, enter an approximate number of additional days that the proposed change would add to the project's current schedule.
In Beta
Note to users participating in the 'Subcontractor Estimated Completion' limited release beta program. When a user places a change order in the 'Approved' status and it includes a value in 'Schedule Impact' field of the change order, Procore automatically updates the 'Estimated Completion Date' field in the commitment contract by the number of days entered.
Field Change Mark this checkbox if the commitment potential change order requires a field change
Reference Reference any other tools, materials, or documents that are related to the commitment potential change order.
Paid in Full Mark this checkbox if the cost is already covered in the budget.
Change Event Line Items If the project is syncing its data with an
In Procore, the term integrated ERP System, is used to refer to Enterprise Resource Planning (ERP) software applications that can be configured to exchange data between Procore and a supported application using the Company level ERP Integrations tool. See Which ERP integrations are supported by Procore?
, select a line item from the Associated Line Item drop-down menu. If you select New Line Item, a zero (0) dollar line item will be added to the commitment's SOV.
If the project is not syncing data with an
In Procore, the term integrated ERP System, is used to refer to Enterprise Resource Planning (ERP) software applications that can be configured to exchange data between Procore and a supported application using the Company level ERP Integrations tool. See Which ERP integrations are supported by Procore?
, continue to the next step.
Click Create. Procore creates the potential change order's SOV using the change event line items.