Add Financial Markup to Commitment Change Orders
Background
To learn about markup, see What is the difference between horizontal and vertical financial markup?
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Commitments tool.
Additional Information:
Financial markup is distributed proportionally on each line item in a change order's Schedule of Values (SOV).
Financial markup is applied to the cost codes and categories on those SOV lines in the budget.
Horizontal markup is included in the SOV's subtotal and is included in the vertical calculation when the markups are used in conjunction.
Limitations:
After you apply financial markup to a commitment change order, the change order cannot be added to a subcontractor invoice.
Prerequisites
Steps
Navigate to your project's Commitments tool.
Click the Contracts tab.
Locate the purchase order or subcontract to work with. Then click its Number link to open it.
Click Financial Markup.
Notes
If the 'Financial Markup' tab is NOT visible, check the More menu to see if it is listed.
If 'Financial Markup' is not available in the More menu, the feature is likely disabled on your project. To learn more, see Enable Financial Markup on a Commitment.
Under Financial Markup Settings, you have these options:
Add Horizontal Markup. Click this button to display the markup in the same row as the line items.
Add Vertical Markup. Click this button to display the markup below the line items.
Notes
To learn about the differences between markup types, see What is the difference between horizontal and vertical financial markup?
You can apply financial markup settings on a per-change order basis.