Bulk Edit Resource Assignments
Things to Consider
You can manage user visibility of assignments with assignment request statuses. See Configure Assignment Request Statuses for Resource Planning.
Assignment alerts are not sent to assignees when bulk editing resource assignments.
Steps
You can bulk edit assignments from the following places:
Bulk Edit Assignments from the Assignments Boards
Navigate to the Company level Resource Planning tool.
Click Assignments and select Boards.
Click Batch.

Click Configure.
Update the information for any of the following fields:
Project. Enter the project that the assignment is for.
Status. Select the assignment status.
Start Date. Enter the date the work assignment starts.
End Day. Enter the date the work assignment ends.
Date. Enter the specific end date for the assignment.
Weeks. Enter how many weeks the assignment is for.
TBD. If the assignment doesn't yet have an end date.
Allocation Type. Select whether the Allocation Type is in Hours of Percent.
Work Hours Start. If you selected 'Hours', enter the time of day the assignment begins.
Work Hours Start. If you selected 'Hours', enter the time of day the assignment ends.
Percent. If you selected 'Percent', enter the percent allocated to the assignment.
Working Days. Move the toggle to the ON position to edit the working days. Then mark the checkboxes for the working days for the selected assignments.
Assignment Alerts. Choose Send Instantly, Save as Draft, Schedule or Don't Send.
Click Set.
Click the Assignments you want to update with the new information.

Click Apply Changes.

Bulk Edit Resource Assignments from the Assignments Gantt (Beta)
In Beta
This feature is in beta and available for customers using the Resource Planning tool.
Importante
No momento, os alertas de atribuição não são enviados ao alterar atribuições dessa maneira.