What happens to projects when I change the segment order of my company's budget code structure in WBS?
解答
当在公司级别管理员工具中重新排列细分顺序时, 如果 在公司级别的细分顺序更改 后将 细分添加到项目的预算编号结构中,则该更改 只会 影响现有项目的细分顺序。
Examples
How the company level budget code structure is inherited on new projects
Your company's Procore Administrator has defined your company level budget code structure as A.B.C.D.
When you create a new project (Project 1) it will inherit the current company's budget code structure. Your project's budget code structure is A.B.C.D.
How rearranging the company level budget code structure affects new and existing projects
Your company's Procore Administrator has defined your company level budget code structure as A.B.C.D.
Before creating a new project, your Procore Administrator changes company level budget code structure from A.B.C.D. to C.B.D.A.
On your existing project (Project 1), the budget code structure remains as A.B.C.D.
When you create a new project (Project 2), it will inherit the current company level budget code structure of C.B.D.A.
How removing project and company segments affects new and existing projects
Your company's Procore Administrator has defined your company level budget code structure as A.B.C.D.
Before creating a new project, your company's Procore Administrator removes segment D from the company level budget code structure. The company level structure is now A.B.C.
A new project is created and inherits the company level budget code structure of A.B.C.
A user with 'Admin' level permission on the Project Admin tool removes 'B' from the project level budget code structure. The project level budget code structure is now A.C.
Any existing projects (projects created before step 2) retain the budget code structure of A.B.C.D.