Assign a Budget View to a Procore Project
Background
While creating or editing a budget view in the Company level Admin tool, your company's A Procore Administrator is a user who has 'Admin' level permissions on all of the Company level Tools in Procore. Granting a user ‘Admin’ level permissions in the Company level Directory tool automatically assigns that user ‘Admin’ permissions on all Company level tools. Also called a Company Administrator.
Things to Consider
Required User Permissions:
'Admin' level permissions on the Company level Admin tool.
Steps
Budget View Page
On the 'Budget View' page, click the hyperlink (e.g., 0/27 Projects) under Assigned Projects.
In the Assign View to Projects modal, select one of the following options from the drop-down list:
Only specific projects. Select this option to manually assign the view. Use the search bar or scroll through the list to mark the checkbox next to each project you want to assign.
Note: By default, this option is selected.Assign to all new & existing projects. Select this option to automatically assign the budget view across all current and future projects.
Note
If your selection includes project templates, the budget view is carried over to new projects created using those templates. See Carry Over Budget Views from a Project Template.
Click Save Changes.
Budget Views Tab
Navigate to the Company level Admin tool.
Under 'Tool Settings', click Budget.
In the 'Budget Views' table, click the hyperlink (e.g., 0/27 Projects) under the Assigned Projects column next to the desired budget view.
In the Assign View to Projects modal, select one of the following options from the drop-down list:
Only specific projects. Select this option to manually assign the view. Use the search bar or scroll through the list to mark the checkbox next to each project you want to assign.
Note: By default, this option is selected.Assign to all new & existing projects. Select this option to automatically assign the budget view across all current and future projects.
Note
If your selection includes project templates, the budget view is carried over to new projects created using those templates. See Carry Over Budget Views from a Project Template.