Create a Commitment Change Order from a Change Event
Background
In Procore, a A Change Event is any event resulting in a modification that affects the scope of work on a construction project and the project's schedule and/or cost(s). In Procore, a change event can be recorded in the system and precedes the creation of a change order, which allows your team members and stakeholders to prepare for a cost change before it becomes an actual cost.
You can create a commitment change order from a change event either before or after the associated RFQ has been responded to or reviewed. However, if you wait until after the RFQ has been reviewed and the RFQ status is set to 'Pending Final Approval,' the change order's Schedule of Values (SOV) automatically populates with the amounts from the RFQ during the change order creation process. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and change order amounts?
The process you use when managing changes in Procore also depends upon how your project's commitment change order tiers are configured. To learn more, see What are the different change order tier settings in Project Financials?
If your project is using the one (1) tier change order configuration, you will only need to create a CCO. See Create a Commitment Change Order. Note: If you are using the DocuSign integration, please see Complete a Commitment Change Order with DocuSign® instead.
If your project is using the two (2) tier change order configuration, first you will Create a Commitment Potential Change Order from a Change Event. Next, you will create a CCO from the Commitments tool. See Create a Commitment Change Order.
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Commitments tool.
'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow Standard Level Users to Create CCOs' configuration must be selected.
Steps
Navigate to the project's Change Events tool.
Select one or more change event line items you want to include in the change order.
Note: You can select line items across multiple change events. You can also use the Filter drop-down to filter by vendor.Choose Bulk Actions > Create a Commitment CO.
Note: The line items on the change order's SOV is created from line items on the change event.Complete the following information:
Number
This field automatically populates based on the number of change orders already created. By default, the number will automatically increment by one.Tip
How does Procore assign numbers to commitment change orders? To learn more, see Can I customize the numbering system for financial objects in Procore?
Revision
This field displays the change order's revision number. When a change order is first created, its revision number is zero. A change order could have multiple revisions because of feedback from a reviewer/approver. This field must be manually entered as revisions are not automatically tracked.
Title
This field will automatically populate with the name of the change event.
Status
Select the current state of the change order. Procore's default status is Pending-In Review.
Note to users with the Claimable Variations feature enabled.
Procore's new Pending - billable status allows you to invoice an amount immediately while the Change Order remains unapproved. This status automatically makes the Schedule of Values (SOV) editable and is exclusively available for single-tier Change Orders on Commitments and Prime Contracts. See Update the Tool Settings for Contracts & Change Orders.