Add Scheduled Work Log Entries (Android)
Hintergrund
The Scheduled Work section allows you to track information for the project resources scheduled to complete tasks. For each resource, you can record details such as their presence at the job site (for example, showed up or did not show up), the number of workers involved, hours worked, and the compensation rate. You must add resources using the project's Directory tool. See Add a User Account to the Project Directory.
Dinge, die Sie beachten sollten
Required User Permissions:
To create entries:
'Standard' or 'Admin' level permissions on the project's Daily Log tool.
OR
To create pending entries as a collaborator:
'Read Only' or 'Standard' permissions to the Daily Log tool with the 'Collaborator Entry Only' granular permission enabled on your permission template.
See Create Daily Log Entries as a Collaborator.
Additional Information:
Entries made by collaborators are marked as 'pending' until approved by an administrator.
There are additional workforce labor categories that can be added to the Daily Construction Report in the Daily Log: (e.g. Women, Veteran, Minority, First-Year Apprentice, Local (City), and Local (County)).
In order to track hours for these additional workforce labor types, these fields must first be configured in the Daily Log section of the Company Admin tool, and then applied to one or more projects.
See How do I enable additional workforce labor types for the Daily Log?
Note: After configured and applied, a 'Workforce Hours' column will be available with a link to 'Add Hours' link will appear in the Daily Construction Report section.
Sie können konfigurieren, welche Elemente mit dem Symbol für die Schnellerfassung
erstellt werden, siehe Einstellungen für die Schnellerfassung konfigurieren.Diese Aktion kann offline durchgeführt werden. Aufgaben, die offline ausgeführt werden, werden mit Procore synchronisiert, sobald eine Netzwerkverbindung wiederhergestellt ist.
Steps
Open the Procore app on an Android mobile device and select a project.
The Tools screen loads, displaying all tools available for this project.Tap the quick create
icon and select Scheduled Work.
OR
Tap the Daily Log tool. Tap the create
icon, then tap Scheduled Work Entry.Tap into the following fields to enter the relevant information:
Note: Click the caret icon > to expand and v to collapse the field names and their descriptions below.
Tap Save.
The log entry is created or added.
Tip
Click Fix Errors to navigate to the first empty required field (if the required fields are empty or blank).
Click Next Field or Previous Field to view other empty fields. Once all required fields are filled, you are able to create or save the form.