In Procore's WBS, a In Procore, a Budget Code is applied to line items in Procore's Financial Management tools to give you the ability to categorise your financial line items as costs in your budget. A budget code in Procore consists of two (2) default segments (i.e., cost code,cost type) and an optional sub job segment. Depending on the company or project level budget code structure in Procore's Work Breakdown Structure, a budget code may also include an unlimited number of custom segments.
What are the components of a budget code in Procore's WBS?
What do budget codes look like?
How are segments delimited in WBS?
How do I create budget codes?
When can I start creating budget codes in Project Financials?
Which Project Financials tools have a 'Create Budget Code' button?
Do I need any additional permissions to create budget codes in Project Financials?
Why can't I import new budget codes into Procore?
What are the components of a budget code in Procore's WBS?
In Procore's WBS, the components of a budget code are called segments. See What are segments and segment items? Using the Admin tool, your company's Procore Administrator can define which segments are part of a budget code by first defining a budget code structure to use at the company or project level. By default, there are two (2) required segments: cost code and cost type. These are required at both the company and project level. There is also one (1) optional project level segment: sub job. The sub job segment can only be enabled at the project level. See Enable Sub Jobs on Projects for WBS.

What do budget codes look like?
With Procore's WBS, your budget code can be simple or complex, depending upon the number of segments required by your company or project level budget code structure. It really depends upon the type of financial information that you want your teams to capture and track for your organisation and for your organisation's construction projects. To learn more about segments, see What are segments and segment items?
The example below shows you a budget code structure with three (3) segments. Note that the cost code tier is a tiered segment.