Create a Change Order (CCO)

Background

In Procore, and are called commitments. A commitment is a contractual agreement between a buyer (for example, a project owner, a general contractor, or a specialty contractor) and a seller (for example, a contractor, a subcontractor, or a vendor). The seller is responsible for completing project work or fulfilling an order for the buyer. When you need to alter the terms of the original agreement, you can create a commitment change order.

 Important

When the Change Events tool is enabled on a project

The process that you will use to create a commitment change order in Procore depends upon a few factors. First, if the Change Events tool is disabled on the project, you will use one of the processes below. Also, keep in mind that the number of steps required to create a commitment change order is dependent upon the change order tier setting that is configured on the project's Commitments tool. See Configure the Number of Commitment Change Order Tiers:

  • 1-Tier configuration:

    1. Create a commitment change order as described below.

  • 2-Tier configuration

    1. Create a commitment potential change order

    2. Create a commitment change order

Things to Consider

Prerequisites

Steps

Create a Commitment Change Order

If you have created a purchase order or a subcontract and need to alter the terms of that item, use the steps below to create a commitment change order.

  1. Navigate to the project's Commitments tool.

  2. Under Contracts, locate the commitment. Then click Edit.

  3. Click Create Commitment CO.

     Notes

    If the Change Events tool is enabled on your project, the Create Commitment CO button is not available. Follow these steps instead:


    Create Commitment Change Order

  4. In the General tab, do the following:

    • Sign with DocuSign®
      If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.

       Tip

      How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.

    • Number
      This field automatically populates based on the number of change orders already created. By default, the number will automatically increment by one.

       Tip

      How does Procore assign numbers to commitment change orders? To learn more, see Can I customize the numbering system for financial objects in Procore?

    • Revision

    • Displays the change order's revision number. When a change order is first created, its revision number is zero. A change order could have multiple revisions because of feedback from a reviewer/approver.

    • Date Created
      Automatically populates with the date that you create the commitment change order. The date cannot be changed.

    • Created By
      Automatically populates with the name of the user who is creating the change order.

    • Contract Company
      Automatically populates with the name of the subcontractor or vendor listed on the subcontract. This field is only available for subcontracts.

    • Contract
      Automatically populates with the name of the contract for which the change order is being created. This field is only available for subcontracts.

    • Title
      Enter a name for the change order. The maximum character limit is 255 characters.

       Important

      If you are using an integrated ERP system, the maximum character limit for the 'Title' field on a commitment is different for each system. For a list of each system and its limitation, see What is the maximum character length for a commitment's 'Title'?

    • Status
      Select a status for the change order. To learn more, see What are the default statuses for change orders in Procore?

    • Private
      Mark this checkbox to make the change order visible only to users with 'Admin' level permissions on the Commitments tool.

    • Change Reason
      Select one of these reasons for the potential change order: Client Request, Design Development, Allowance, Existing Condition, or Backcharge. To learn how to configure change reasons, see Set Default Change Management Configurations.

    • Accounting Method
      This field inherits the accounting method that was specified in the contract.

    • Due Date
      Select a due date for when the change order must be approved by.

    • Invoiced Date
      Select the date when the change order was invoiced.

    • Designated Reviewer
      Select the Procore project user at your organization who will be responsible for approving or rejecting this change order later. See Approve or Reject Commitment Change Orders.

       Important
      • The 'Designated Reviewer' can submit an approve or reject response only when a change order is in the Pending - In Review status.

      • To send an email notification to the 'Designated Reviewer' to notify that person that a change order is awaiting their response, you have these options:

        • You can forward the prime contract change order to the 'Designated Reviewer' by email. See Forward a Change Order to a Project User by Email.
          OR

        • The pending change order will also be listed in the 'My Open Items' area in the project's Home page. The user can check this page at any time.

      • After the 'Designated Reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'Designated Reviewer' field) shows the date/time stamp of that users response. The 'Reviewer' field is only visible to the 'Designated Reviewer.'

    • Request Received From
      Select a user from the project's directory who you are submitting the change order on the behalf of.

    • Description
      Enter a detailed description of the change order.

       Notes
      • If you are exporting the change order to Sage 300 CRE® and Integration by Procore, entries exceeding one thousand (1000) characters will be truncated during the export.

      • If you will be exporting the change order to a different integrated ERP system, you can to enter an unlimited number of characters in Procore.

    • Schedule Impact
      If known, you can provide an estimate of the number of additional days that would potentially be added to the current project schedule if the change order were approved.

       In Beta

      Note to users participating in the 'Subcontractor Estimated Completion' limited release beta program. When a user places a change order in the 'Approved' status and it includes a value in 'Schedule Impact' field of the change order, Procore automatically updates the 'Estimated Completion Date' field in the commitment contract by the number of days entered.

    • Location
      Use the location drop-down menu to select a location the [item] impacts. Either select from the predefined locations, or add a multi-tiered location. See Add a Multi-tiered Location to an Item. This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier.

    • Reference
      Reference any other tools, materials or documents that are related to the change order.

    • Executed
      Mark this check box if the change order has already been executed.

    • Field Change
      Mark this check box if the change order requires a field change.

    • Paid in Full
      Mark this check box if the cost is already covered in the budget.

    • Attachments
      Select and add any relevant documents.

  5. Click Create or Create & Email to send the change order to any users listed as 'Reviewers'.

Add a Schedule of Values (SOV) to the Change Order

If there are costs associated with the change order, add line items to the change order's Schedule of Values (SOV).
Add Commitment Schedule Of Values

  1. Click the Schedule of Values tab.

  2. Click Edit.

  3. Click Add Line.

    • Prime Contract Line Item
      Select a line item from the drop-down list. If there is no line item that fits, select Not Budgeted.

    • Change Event Line Item
      Select a change event line item from the drop-down list.

    • Sub Jobs
      If the Sub Jobs feature is enabled on your project, select one from the list. See Enable Sub Jobs on Projects for WBS.

    • Budget Code
      Select a budget code from the drop-down list. See What is a budget code in Procore's WBS?

    • Description
      Type a description for the new change order.

    • Cost Amount
      Enter an amount in the box.

    • Optional: Tax Codes
      If you are using tax codes with this project, select a tax code to use for the line item.

       Tip

      Don't see the Tax Codes field? This field only appears when the tax codes feature is enabled on the Procore project. See How can I use tax codes on a project?

  4. Click Add

  5. Repeat these steps for each line item.

  6. Click Save.

 Note

For Companies That Have Enabled the ERP Integrations Tool

After the commitment change order is placed into the 'Approved' status in the Commitments tool, project managers will typically send the change order to the ERP Integrations tool where it must be accepted by an accounting approver for export to the integrated ERP system. For instructions, see Send a CCO to ERP Integrations for Accounting Acceptance.

Next Steps