Copy Company Cost Codes to a Project

Background

A Cost Code identifies a specific type of work on a project to track its associated expenses, such as labor, materials, and equipment.

Things to Consider

  • Required User Permissions:

    • You need one of the following:

      • 'Admin' level permission on the Project level Admin tool.

      • 'Read Only' or 'Standard' level permissions on the project level Admin tool with the 'Manage WBS Codes' granular permission enabled on your permissions template.

  • Limitations:

    • For customers using the Company level ERP Integrations tool
      The default segments in WBS are compatible with Procore's tool. However, some integrations do NOT yet support custom segments.

    • For customers who have independently developed or purchased a third-party solution to integrate with Procore
      To take advantage of the custom segment capabilities associated with WBS, any existing API integrations that you have independently developed or purchased to interact with Procore must be updated to support Procore's new WBS API.

Prerequisites

Steps

  1. Navigate to the Project level Admin tool.

  2. Under 'Project Settings', click the Work Breakdown Structure link.

  3. In the 'Segments' list, click the Cost Codes link.

  4. Click Cost Codes from Company.
    Btn Cost Codes From Company

  5. In the 'Add Cost Codes to this Project' window, choose from these options:

    Add Cost Codes To This Project

    • To copy all company cost codes to the project, click Select All.

    • To select specific cost codes, type a code in the Search Cost Codes box and highlight the codes to add.

    • To choose cost codes, expand the desired segment items and highlight the segment items to copy.

  6. Click Add.

Next Steps