T&M Tickets and Change Events

Background

Rates are configured in T&M Tickets and applied to Labor, Materials and Equipment entries. When a Change Event is created from a T&M ticket, the revenue unit cost in each change event line item is pre-populated based on the rates from the T&M entries.

These cost rates are visible in the Change Event in the Change Events tool.

Rates are applied when the rate is in the rate table that is assigned to the project.

Things to Consider

Steps

  1. Navigate to the project's T&M Tickets tool.

  2. Click the configure settings Icon Settings Gear Grey3 icon.

  3. Optional: Click Sync Cost Rates to sync the rates from your Timesheets settings.

  4. Under 'Labor Rates,' select the rate to apply to each time type in T&M Tickets.

  5. Under 'Equipment Rates,' select the rate to apply to Operating and Idle Hours in T&M Tickets.

  6. Under 'Material Rates', select the rate to apply to materials in T&M Tickets.

  7. Click Update.