Delete a Prime Contract Change Order
Background
To delete or remove a PCCO, you can click the Actions or the vertical ellipsis icon next to the PCCO and select the Delete icon. However, when the icon is grayed out and not available, it means the PCCO is associated with other items in Procore. The steps below show you how to remove associated items and then permanently delete a PCCO.
Before you can perform a delete action, you must:
Change the status of the PCCO from 'Approved' to another status as described below. If you want to change the status of multiple PCCOs, you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002, and 003), you will need to remove the 'Approved' status in reverse order (003, 002, 001).
Unlink any Procore items associated with the PCCO. This may include Potential Change Orders (PCOs), Change Order Requests (CORs), and invoices as described in the Prerequisites below.