Remove a Change Order from a Prime Contract

Background

Before you can remove a Prime Contract Change Order (PCCO) from Procore (as described in Delete a Prime Contract Change Order), you must use the Steps below to remove any PCOs or CORs linked to that PCCO.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the project's Prime Contracts tool.

Prerequisites

  • Before changing the status of multiple PCCOs from 'Approved' to another status, be aware that you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002, and 003), you will need to unapproved them in reverse order (003, 002, 001).

  • If any change orders have been added to your project's invoices, you must delete those invoices before you can use the steps below.

Steps

  • Navigate to the Change Orders Tab

  • Change the Status of the Prime Contract Change Orders from 'Approved'

  • Unlink Potential Change Orders and Change Order Requests

  • Delete the Potential Change Orders and Change Order Requests

Navigate to the Change Orders Tab

  1. Navigate to the project's Prime Contracts tool.

  2. Locate the prime contract to work with. Then click its Number link.

  3. Click the Change Orders tab. Depending on the number of change order tiers configured for the tool, the following tables appears in the tab:

    • Prime Contract Change Orders

    • Potential Change Orders

    • Change Order Requests

Change the Status of the Prime Contract Change Orders from 'Approved'

 Important

Before changing the status of multiple PCCOs from 'Approved' to another status, be aware that you must apply the status changes in reverse order from how they were approved. For example, if you approved the PPCOs in sequential order (001, 002, and 003), you will need to remove the 'Approved' status in reverse order (003, 002, 001).

  1. In the Prime Contract Change Orders table, locate the 'Approved' PCCOs.

  2. Click View to open the PCCO.

  3. Click Edit.

  4. In the Status drop-down list, change the status from 'Approved' to a different status.

  5. Click Save.

Unlink the Potential Change Orders and Change Order Requests

  1. Scroll to the Potential Change Orders Included in this PCCO section.

  2. Locate the COR or PCO to work with. Then click View.

  3. Click Edit.

  4. Scroll to the Prime Contract Change Order drop-down list as shown below.

  5. Choose None.
    Pcco None

  6. In the Potential Change Orders list, remove all of the existing PCOs from the list:

    Pconone2015 03 20 10 25 50

  7. Click Save.

Delete the Potential Change Orders and Change Order Requests

  1. Return to the Change Orders tab.

  2. Locate the PCO or COR to remove.

  3. Click the red (X) next to each PCO or COR to remove.
    Delete Prime Contract Change Order

  4. In the confirmation dialog box that appears, click OK to confirm the removal action for the selected PCO or COR.

Next Step

See Also

Loading related articles...