How are the date columns in submittal custom reports calculated?

Answer

  • Approver due date variance

    • When a submittal is closed, this column is equal to approver return date - approver due date

    • When a submittal is open, this column is equal to Current date - approver due date

  • Approver returned date duration

    • When as submittal is closed, this column is equal to approver returned date - approver sent date

    • When a submittal is open, this column is equal to Current date - approver sent date

  • Ball in Court duration

    • When a submittal is open, this column is equal to Current date - Ball in Court sent date