Answer

By default, the following columns are available in the Contracts tab of the project's commitment tool. While you can't add or remove columns from the tool, you can choose which columns to show or hide.

Example

The illustration below shows you the column headings in the project's commitment tool.

Commitments Contracts Columns

Default columns

This table details the default columns in the Contracts tab of the project's commitments tool.

Column name

Column format

Details

Number

Number

Shows the commitment number.

Contract company

Text

Shows the name of the company responsible for completing the work for the commitment.

Title

Text

Shows the name entered in Procore for the commitment.

Status

-

Shows the current status of the commitment. To learn about the default statuses, see What are the default commitment statuses in Procore?

Executed

Yes/No

Shows whether or not the commitment has been executed.

Original Contract Amount

currency

Shows the amount for the original commitment.

Approved variations

currency

Shows the amount of all variations associated with the commitment currently in the 'Approved' status.

Revised contract amount

currency

Shows the revised contract amount after any 'Approved' variations.

Pending variations

currency

Shows the amount of all variations in the 'Pending' status.

Draft variations

currency

Shows the amount of all variations in the 'draft' status.

Payment application

currency

Shows the amount that has been payment application.

Payment received

currency

Shows the amount of any payment received.

% Paid

Percentage

Shows the percentage of the commitment amount that has been paid to date.

Remaining balance outstanding

currency

Shows the remaining balance for the commitment. This value is calculated by subtracting the value of the amounts on the 'Payment issued' tab of the payment application from the value in the 'Revised contract amount' cell. Note: To learn about adding payment to the Payment issued tab, see Add a new payment to the Payment issued tab of a commitment

Signatures required

User name

If you have enabled the Procore + DocuSign® integration, this shows the name of the person from whom a signature is pending.

Private

Yes/No

Shows whether or not any privacy setting have been added to the commitment.

1 If you have been assigned the required user permission, you can edit the contents of a cell in this column inline.

Additional columns

This table details the additional columns in the Contracts tab of the project's Commitment tool. These columns require specific features to be enabled.

Column name

Column format

Details

Subcontractor Bill of Quantities status

Status

When you enable the Subcontractor BOQ tab on a commitment, shows the status of the Subcontractor Bill of Quantities (Subcontractor Bill of Quantities).

Procore Pay status

Status

When Procore Pay is enabled, shows the current status of the payee's bank account in the verification process. See What are the default status for Procore Pay onboarding?