What is a partial budget line item?

Answer

A partial budget line item is a new budget line item that includes only a budget code. It is sometimes referred to as a 'non-budgeted', 'unbudgeted' or 'missing' line item, because it was NOT included as a planned expenditure on the project's original Budget. To see an example and learn more, see What is a partial budget line item?

Example

In Procore, a partial budget line item is:

  • A new budget line item that consists of only a budget code as pictured below. See What is a budget code in Procore's WBS?

    Add Partial Cost Code Type

  • Can only be added to a budget after the project's original budget is locked. See Lock a Budget

  • Considered an 'unbudgeted line item' because it is NOT part of the project's original planned expenditures.

After you add a partial line item to a Budget, a question mark (?) appears next to the line item to it so you can find it later, as illustrated below.

Ubli Tooltip

How do I work with partial budget line items?

Important things to keep in mind when working with partial budget line items:

  • When working with partial line items, users are NOT permitted to perform the following actions:

    • Users may NOT edit the Budget unit quantity, Budget UoM or Budget unit cost.

    • Users may NOT edit the original Budget amount.

    • Users may NOT edit the Forecast to Complete value. See Use the 'Forecast to Complete' feature.

    • Users may NOT create budget modifications to transfer funds into or out of unbudgeted line items.

  • To include only partial line items in the Budget tab, add the 'Budget Row Type' filter and then place a tick in the 'Unbudgeted' box.

  • To exclude partial line item from the Budget tab, add the 'Budget row type' filter and place a tick in the 'Budget' box.

  • To learn more about applying filter to a budget view, see Apply the view, Snapshot, group and filter options on a budget view.

  • If a partial line item has not been assigned a cost code or cost type, the word 'None' appears in place of the missing cost code or cost type and the line item is considered to be a partial line item. This is also true when a division is selected as a cost code. Partial line items cannot be added to the Budget.

    • If the financial item associated with the partial line item is still editable, you can return to the point of creation to add the missing cost code or cost type/category.

    • If the financial item is NOT editable, the partial line items remain in the Budget with the question mark (?) symbol.

    • To view partial line items with no cost code assignment in the Budget tab, add the 'cost code' filter and place a tick in the 'None' box.

    • To view partial line items with no cost type assignment in the Budget tab, add the 'Category' filter and place a tick in the 'None' box.