What is a budget code in Procore's WBS?

Answer

In Procore's WBS, a is used in Procore's Project Financials tools to keep track of the costs and revenue for a construction project on your financial line items.

  • What are the components of a budget code in Procore's WBS?

  • What do budget codes look like?

  • How are segments delimited in WBS?

  • How do I create budget codes?

  • When can I start creating budget codes in Project Financials?

  • Which Project Financials tools have a 'Create Budget Code' button?

  • Do I need any additional permissions to create budget codes in Project Financials?

  • Why can't I import new budget codes into Procore?

What are the components of a budget code in Procore's WBS?

In Procore's WBS, the components of a budget code are called segments. See What are segments and segment items? Using the Admin tool, your company's Procore Administrator can define which segments are part of a budget code by first defining a budget code structure to use at the company or project level. By default, there are two (2) required segments: cost code and cost type. These are required at both the company and project level. There is also one (1) optional project level segment: sub job. The sub job segment can only be enabled at the project level. See Enable Sub Jobs on Projects for WBS.

Example

Diagram Wbs Default Budget Code Structure With Sub Job

What do budget codes look like?

With Procore's WBS, your budget code can be simple or complex, depending upon the number of segments required by your company or project level budget code structure. It really depends upon the type of financial information that you want your teams to capture and track for your organisation and for your organisation's construction projects. To learn more about segments, see What are segments and segment items?

Example

The example below shows you a budget code structure with three (3) segments. Note that the cost code tier is a tiered segment.

Diagram Wbs Flat And Tiered Budget Code Structure

How are segments delimited in WBS?

When creating a budget code, it is also important to note that in the Procore web application's user interface, tiered segments are delimited by a dash (-) and segments are delimited by a period (.). In the example below, the tiered 'Cost Code' segment is 01-904 and each tier is delimited by a dash (-). The next segment in the budget code structure is 'Cost Type' and the period (.) is used as a delimiter to separate it from the cost code.

Example Budget Code In Project Financials Tools

Cost Code Tiered Segment

Cost Type Flat Segment

Budget Code

01-904

S=Subcontract

How do I create budget codes?

 Important

First, your company's Procore Administrator must define your company's budget code structure. See Create Your Company's Default Work Breakdown Structure. Next, you must define your budget code structure (you can use your company's default structure or customise one to be project-specific). This step can be performed by a user with 'Admin' level permissions on the Project level Admin tool. See Create Your Project's Work Breakdown Structure.

Once your project's WBS is created, users with the appropriate permissions can then create budget codes in Procore's Project Financials tool. For instructions, see Create Budget Codes for WBS in Procore's Project Financials Tools.

When can I start creating budget codes in Project Financials?

First, your company's Procore Administrator must define your company's budget code structure. Next, a project administrator defines the budget code structure for a project. Once your project's budget code structure is defined, you can begin using Procore's Project Financials tools to create budget codes for the financial line items on your project. See Create Budget Codes for WBS in Procore's Project Financials Tools.

Which Procore tools have a 'Create Budget Code' button?

The 'Create Budget Code' button is supported in Procore's Project Financials tools. Budget Codes created within project financials tools must use the lowest tier segment available EXCEPT for Budget Codes created in the Main Contracts tool.

Procore Project Financials tools

Tutorials

Budget
In the Budget tool when creating or editing a budget line item.

Add a budget line item

Change events
In the General tab when adding or editing a change event line item.

Create a change event

Variations
In the bill of quantities on a commitment variation, a main contract variation, a commitment potential variation or a main contract variation.

Create a commitment variation Create a main contract variation Create a potential variation for a main contract

Client contracts 1
In the Bill of Quantities of a client contract.

Create client contracts

Commitment
In the Bill of Quantities and Subcontractor Bill of Quantities on a purchase order or subcontract.

Create a purchase order Create a subcontract

Direct cost
In the line items section when creating or editing a direct cost.

Create a direct cost

Funding 2
In the Bill of Quantities of a funding.

Create funding

Main contracts In the bill of quantities of a main contract.

Create main contracts

Do I need any additional permissions to create budget codes in Project Financials?

No. To create a budget code, you only need permission to create or edit an item with the corresponding Project Financials tool. For example, to create a budget code while adding a line item to a direct cost, you would need permission to create a direct cost. See Create a Direct Cost. To create a budget code while updating the bill of quantities on a main contract, you would need permission to create a main contract. See Create Main Contracts.

 Important

While you can create new budget code on the fly, the segment item that are part of the budget code must exist in the Company level budget code structure. You cannot add new segment item on the fly. Only a Procore administrator can create a Company level budget code structure and only a project administrator can create a Project level budget code structure (and only if your company's Procore administrator has enabled the 'Project level Actions' setting. See Create your company's default work breakdown structure and Create your project's work breakdown structure.

Why can't I import new budget codes into Procore?

With Work Breakdown Structure, a that comprises a must exist in a in the company level . Instead of importing new budget codes into Procore, your company's Procore Administrator uses the Procore Imports app to import new segment items (for example, cost codes, cost types, sub jobs and custom segments) into your company or project level Work Breakdown Structure.