Create main contracts
Background
A A main contract is a legal agreement between contracted parties. In a single, two-party main contract, the owner financing the construction project is called the client or principal. The party being paid to ensure completion of work is called the general, primary or main contractor. In Procore, you can either create a single main contract for a construction project or you can also divide the scope of work for a single project between multiple main contracts.
In Procore, you can manage a project with either a single or multiple agreements. If the project is large, has multiple funding sources or involves several clients, divide the scope of work into multiple agreements.
If your company has purchased Procore to manage your construction projects, you can create one (1) or more contracts for each new construction project.
When to create a single main contract
Most customers who manage their construction projects in Procore create a single contract for a single project. For example, if you are a main contractor, creating a single contract is the simplest way to manage a construction project when it has a single project owner and a single funding source. If you are an owner/developer or an internal main contractor with an upstream approval requirement, you might choose to create a single main contract to handle the upstream contract and payment applications.
When to create multiple main contracts
If a project has multiple owner/client, funding source and/or project delivery methods, you can also choose to create multiple contracts for a single project. If you choose to create multiple contracts in a single Procore project, there are some limitations. For details, see Are there any system limitations when projects have multiple main contracts? Reasons to create multiple contracts include:
Multiple clients and funding sources. A project can have multiple funding sources or multiple clients. For example, a specialty contractor might choose to create a separate main contract for each client. Or your construction company might have been contracted to complete work on a project with more than one funding stream, such as a private donor, a public grant, a public authority, bonds, grants, loans or a combination of all these examples. See Configure advanced settings: Main contracts.
Multiple stages. A project can be divided into stages. For example, you might require separate contracts for pre-construction, course of construction and aftercare/maintenance.
Multiple phases. A project can be portioned into phases. For example, you might require separate contracts for the foundation, plumbing, HVAC and so on.
Guaranteed maximum price (GMP) contracts. A project can be fast-tracked or a phased GMP job. For example, you might require multiple contracts for each established scope-of-work package.
Construction manager as advisor (CMa) delivery methods. A main contractor operating as a CMa might need to manage multiple contracts between an owner and various contractors.
After you create an agreement, you can then update its Bill of Quantities (BOQ). For details, see Update the bill of quantities on a main contract.
Is the Bill of Quantities on the contract similar to the line item on the project's budget? If so, Procore recommends creating the project's budget before the contract. To eliminate repetitive data entry, you can use the main contract tool's import feature to Create the main contract Bill of Quantities from the project budget.