Create a potential variation for a main contract
Background
When a change to the scope of work or the original main contract amount occurs during a construction project, the change management process begins. You can create a PV if your company's Procore administrator configures the Main Contracts tool with the two (2)- or three (3)-tier variation configuration setting. See What are the different variation tier setting in Project Financials?
Things to Consider
Required User Permissions:
Admin' level permissions on the project's Variations tool.
ImportantDo not use the steps below when:
The change event tool is enabled on the projects. Follow these steps instead: Create a main contract PV from a change event.
The Main Contracts tool is configured with the one (1) tier variation configuration setting. Follow these steps instead: Create a main contract variation.
Additional Information:
After a PV is approved, the next step depends on the main contract tool's variation configuration setting:
For the two (2)-tier variation setting, continue with these steps: Create main contract PV
For the three (3)-tier variation setting, continue with these steps: Create a variation request for a main contract