Background
On a construction project, a change event is any change that affects the original scope of a construction project. It can be any event that affects the scope of the work to be completed, causes a change to the Project Programme or results in unexpected cost. It allows your project's team members and stakeholder to prepare for a cost change before it becomes an actual cost.
Example 1: Create a change event to establish a variation
A change event can come from many sources and is an event that establishes the variation process. Examples include:
Accommodating an owner request.
Accounting for a design flaw.
Addressing an unforeseen issue caused by a vague document or specification.
A change event can also be used to document a project condition that resulted in a Contra charge. The intent of a Contra charge is to recover the unforeseen expenses incurred when performing corrective actions that a party was contractually obligated to perform.
To ensure that you have fully documented the conditions that resulted in the contra charge, you can create a change event. Common scenarios for documenting contra charges this way include:
Repairing something that a subcontractor damaged.
Cleaning up an area that the subcontractor was obligated to clean.
Replacing defective materials provided by the subcontractor.
Reinstalling an incorrect installation performed by a subcontractor.
Bringing a neglected issue into compliance with safety regulations.
Providing unforeseen Equipment rental and use cost.
With the change event tool in Procore, you can create a change event to record a reason for a change in a construction project. They also prepare project team members and stakeholder for the potential cost associated with the change event. After a change event is created, you can then send a request for quote to your subcontractors. Subcontractors can then respond to RFQs (or a main contractor can enter a response to an RFQ on the subcontractor's behalf). Included in the RFQ response is all the required documentation related to the change event's potential cost and programme impact. After your subcontractor's RFQs responses are reviewed, your project team has the information it needs to proceed with creating a potential variation.
Things to Consider
Required User Permissions:
'Standard' level permissions or higher on the project's change events tool.
Change event #: Procore automatically assigns numbers to change event in ascending order.
Note
The default numbering scheme is 001, 002, 003 and so on.
You can customise the numbering scheme for the change events on your project at any time by typing an alphanumeric numbering scheme over the default value. For example, CE001, CE1000, CE-1000 and so on.
After customising the numbering scheme, Procore uses your new scheme to assign numbers to new change events.
Title: Enter a descriptive title for the change event.
Description: Describe the event that may result in a change in cost.
Attachments: Attach any relevant files.
Main contract (for markup estimates): Select a main contract to indicate which main contract’s markup setting should be used to calculate the markup on rough order of magnitude. This field will default to the lowest-numbered main contract.
Optional: If you want to add line items to your variation now, follow the steps in Add change event line items.
Click Create.
Add change event line items
Tip
Did you know a user with 'admin' setting on the change event tool can turn the change event tool's 'Column display' setting ON and OFF? For best results, your project's column display setting should be determined at the beginning of a project. To learn more, see How do the change event tool's column display setting work?
Navigate to the project's change event tool.
Choose from these options:
Click the Detail tab. Then find the change event to update and click Edit. OR
Follow the steps in Create a change event.
Choose from these options:
To add a new line item, click Add line. OR
To add line items in bulk using line items from all of the project's commitments in the 'Approved' status, click Add lines for all commitments.
Complete the line item data entry as follows:
Tip
You can group change event line items while editing a change event by clicking Add group at the top of the line item adder. You can group line items by the following:
If you are using the enhancements for unit-based financials, this column will capture unit changes to UoM on both Rev ROM and cost ROM.
If you follow those steps to show the ROM value in the budget and the change event line item ends up having no cost, you will need to zero (0) out the ROM to remove it from the budget.
Click Update.
Note: If the combination of the sub job, cost code and cost type are non-budgeted, a pop-up will appear asking to confirm to add these line items to the Budget. If OK is selected, these line items will be added directly to the Budget with a "?" next to each line item. See Add a partial budget line item.