What is a partial payment?

 General availability in select markets (United States)

Flag Us Procore Pay is available in the United States. It is designed for main contractors and owner-builders who act as their own main contractors on a job. Procore Pay extends the payment application management functionality in the Procore web application to handle the payment process between main and specialty contractors.

Answer

A partial payment covers a portion of a payee's cost for completing work, securing resources or achieving milestones. Partial payment assure payees of consistent cash flow and payors of steady project progress.

Examples

Scenarios where a payor might issue partial payment to payees include:

  • Material and Equipment procurement. To secure long-lead, expensive or specialised items or materials.

  • Milestone or phase completion. When milestones or distinct phases of work are completed.

  • Offsite fabrication. To cover labour and material cost for custom component fabrication.

  • Substantial progress. Upon inspection of significant progress, such as milestone completion.

  • Contractual Payment Programme. As dictated by agreed-upon Payment Programme within the construction contract.