Which data columns are in a Field Production report?

Answer

The Field Production report provides Procore users with the ability to compare a construction project's Budget production quantities with its installed production quantities. With the appropriate permissions, you can view this report with the project's 360 Reporting or timesheets tool. See View a Field Production report.

 Notes
  • For customers using Procore's Resource tracking and Project Financials tools, production quantities and hours entered on your project's variations automatically update data in these Procore features, when variations are placed in the 'Approved' status:

    • The Procore labour productivity cost budget view.

    • The field production report. See Which data columns are in a field production report?

Field production report columns

The following image shows you a field production report.

Field Production Report

The following table details the report columns in the 'Field production report.' It also details how calculation and configured in each column. You cannot customise the columns in this report.

Report section

Column name

Column type

Column format

Column description

Column configuration

Hours

Revised Budget hours (RBH)

Source

Number

Shows the Budget number of hours for the cost code.

-

Hours

Actual (AH)

Source

Number

Shows the actual number of hours entered to date for the cost code.

-

Hours

Remaining hours (RH)

Calculated

Number

Shows the remaining number of hours for the cost code.

Budget hours subtract (-) actual hours

Hours

Percent used

Calculated

Percentage

Shows how much of the current Budget unit quantity (labour hours) have been used based on time submitted in Procore.

Timesheet hours divide (/) revised Budget unit quantity

Hours

Projected at completion

Calculated

currency

Shows the estimated labour hours needed to complete production for the cost code based on the work produced to date.

(Remaining quantity divide (/) actual production rate) add (+) actual hours

Hours

Earned hours 1

Calculated

Number

Shows the number of labour hours earned (merited) based on the work produced to date for that cost code.

(Budget Hours multiply (*) Actual quantity) divide (/) Revised Budget quantity

Quantity

Revised Budget quantities (RBQ)1

Source

Number

Shows the Budget production quantity for the cost code.

-

Quantity

Actual (AQ)

Source

Number

Shows the actual production quantity to date for the cost code.

-

Quantity

UoM

Source

N/A

Shows the UoM for the cost code

Source category: Production UoM source: Budget production UoM source filtering: n/a

Quantity

Remaining (RQ)

Calculated

Number

Shows the remaining production quantity for the cost code.

Budget production quantity minus (-) remaining production quantity

Quantity

Percent Complete

Calculated

Percentage

Shows the percentage of the production quantity has been installed to date of the current Budget production quantity for the cost code.

Actual quantity installed divide (/) revised Budget production quantity

Production rate

Budget (BPR) 1

Calculated

Number

Calculates the production rate based on the Budget number of hours and Budget quantity.

Budget production quantity divide (/) revised budget hours

Production rate

Actual (APR)

Calculated

Number

Calculates the actual production rate based on the actual number of hours and installed production quantities updated in Procore to date.

Actual quantity installed divide (/) actual hours

Production rate

Variance

Calculated

Number

Calculates the difference the actual and Budget production rate.

Actual production rate minus (-) Budget production rate

1 If the project has any variations in the 'Approved' status, the 'Budget (BQ)' column label changes to 'Revised Budget (RBQ)'. In addition, the RBQ is used to calculate the values in the Budget production rate (BPR) and earned hours columns.