Details

Key features include the ability to:

  • Configure ‘budget changes’ settings in the 'Budget settings' page of the project's Budget tool

  • Add a new 'Budget change value' column and 'Budget change' group on the main contract payment application Bill of Quantities

  • Create a new budget change and select the main contract so it can be added to the main contract payment application once the change is approved

  • Respond to the notification banner on the most recent main contract payment application's Bill of Quantities by clicking Review & Add

  • Review the approved changes and select the changes to add to the most recent main contract payment application

  • View and edit the added changes on the most recent main contract payment application

Configure the 'budget change' setting in the 'Budget setting' page of the project's Budget tool

To add approved budget change to the most recent main contract payment application, an administrator must configure the 'budget change' setting in the 'Budget setting' page of the Project level Budget tool. See Configure setting: Budget:

  • Allow budget changes to be billed on main contract payment applications. Adds the 'Budget change value' column to the bill of quantities on main contract payment applications, adds the 'Add to main contract payment application' tickbox and 'Main contract' drop-down list to the 'Add budget changes' window and enables the budget change notification banner to appear at the top of the most recent main contract payment application's Bill of Quantities' after a change is approved. See Approve budget changes.

     Note

    Once approved, only Net Zero budget changes are eligible for adding to main contract payment applications.

Example

Below are the new 'budget change' configuration options in the 'Budget settings' page of the Budget tool.

Budget Changes Budget Settings

Add a new 'Budget change value' column and 'Budget change' group on the main contract payment application Bill of Quantities

After an administrator configures the 'Budget changes' settings, the 'Budget change value' column appears in the project's main contract payment applications when you expand the 'Value' column group. This column can be turned ON/OFF in the 'Configure columns' area under 'Value' on the Table settings panel of a payment application's Bill of Quantities. By default, the column is turned ON, but the 'Value' column is collapsed. To see it, expand the 'Value' column. A 'Budget changes' group is also available in the Select groups to display drop-down list.

Example

Below is an example of the 'Budget changes value' column and 'Budget changes' group on a main contract payment application.

Budget Changes On Owner Invoice Sov

Create a new budget change and select the main contract so it can be added to the main contract payment application once the change is approved

After an administrator configures the 'budget change' settings, a new 'Add to main contract payment application' tickbox and 'main contract' drop-down list on the 'General information' card in the Create new budget change form. Marking the 'Add to main contract payment application' tickbox lets Procore know to add the budget change to a main contract payment application after approval. Users must also select a main contract so Procore can display the notification banner to alert users to review and add the approved changes to a main contract payment application.

Example

Below is the 'Create new budget change' page in the project's Budget tool, with the 'Add to main contract payment application' tickbox and 'Main contract' drop-down list.

Create New Budget Change Add To Invoice

Respond to the notification banner on the most recent main contract payment application's Bill of Quantities by clicking Review & Add

When a user edits the most recent main contract payment application for a main contract, a notification banner appears at the top of the Bill of Quantities on the main contract's main contract payment applications when newly approved budget change are available to add to an existing main contract payment application. Users can only click the Review & Add button on the most recent payment application. For all older payment applications, the notification banner appears to alert the user of newly approved changes, but the Review & Add button is disabled by default. You can only review & add changes on the most recent payment application.

Example

Below is an example of the notification banner and the Review & add button that displays on the selected main contract's main contract payment applications. The Review & Add button is only active on the most recent payment application.

Banner Review And Add Active

Below is an example of the Review & add button when its disabled. Hover your mouse cursor over the button to see a tooltip.

Banner Not The Most Recent Invoice

Review the approved changes and select the changes to add to the most recent main contract payment application

After clicking the Review & add button on the most recent payment application, the 'Review & add approved changes' window appears. Users can mark the tickboxes that correspond to the budget change to add. If there are multiple budget changes or variations, all approved changes are listed. After selecting the changes to add, click Add. A green banner appears to confirm the addition(s).

 Note

If you create a new main contract payment application after approving budget changes, all approved changes are automatically reflected on the payment application. You only need to add approved changes to the most recent, existing main contract payment application.

Example

Below is the 'Review & add approved changes' window. It lists all newly approved budget changes and variations. You can use the main contract payment application's bulk billing features when editing the most recent main contract payment application.

Review And Add Budget Change

View and edit the added changes on the most recent main contract payment application

Once you've added the budget change(s), they appear in the 'budget change' group in the Bill of Quantities. Users can bill against the budget codes that were adjusted by the budget change by editing the line item directly or using the bulk billing features. To learn more, see Edit main contract payment applications.

Example

Below is an example of a budget change after it's been added to a main contract payment application's Bill of Quantities.

Budget Changes In Sov

View a tooltip for details about the 'Scheduled value' calculation for the main contract payment application's Bill of Quantities

After an administrator configures the 'budget changes' settings, hover your mouse cursor over the information icon on the 'Scheduled Value' column on the payment application's Bill of Quantities. A tooltip that explains how the 'Scheduled value' calculation is update when your team is adding budget change to main contract payment applications.

Example

Below is an example of the 'Scheduled value' tooltip on the Bill of Quantities of a main contract payment application.

Scheduled Value Tool Tip