Imported materials and materials listed in approved orders from the commitment tool appear in the Materials tool. From the Materials tool, you can create receipts to track the materials you have received. After all materials have been received, post the receipt to indicate that receiving is complete.
For companies with Procore Financials, a draft payment application is automatically created in Procore's Payment Applications tool after you post the receipt.
After you post the receipt, a draft payment application is automatically created in Procore's Payment Applications tool.
Navigate to the project's Materials tool.
Click the Control tab.
Click the Receipts subtab.
Click the receipt number.
Locate the 'Document status'.
Click Not posted and select one of the following options:
Select Post to add the materials to your inventory. In the future, you can issue materials for handover.
Select Post > Direct Handover to Person to automatically issue and handover the materials.
Select Post > Direct Handover to Project to automatically issue and handover the materials.
If you have an open valuation period, a draft subcontractor payment application is automatically created in Procore's Payment Applications tool after the receipt is posted. However, if a valuation period is not open at the time the receipt is posted, a draft payment application will not be created, even if a valuation period is opened at a later date.
Procore recommends that you do NOT manually create payment applications for materials, as it will create a duplicate. The payment application automatically generated from the receipt cannot be deleted.