You can automatically create viewpoint for each clash to provide consistency and streamline your workflow. You can create viewpoint for specific clash status, so that you can focus on the most important issues. Viewpoint are saved to a time-stamped folder, creating a clear record in time. You can create 3 different types of viewpoint: 3D View, Orient Plan View and Isolate View.

Important

To use Procore Clash Manager for Navisworks® on a Windows® computer running your Autodesk® software, you must Download & install the Procore BIM plugin.

Things to Consider

  • Required User Permissions

  • Additional Information:

    • Best practice is to choose the folder structure for Assignment, then Test. Folders are created for individuals assigned with sub-folders for each clash test.

Steps

  1. Click viewpoint in Clash Manager.

  2. Select the clash tests you want to create viewpoint for.

    • All tests

    • Selected tests to create viewpoint for the clash tests currently selected.

  3. Select how you want your viewpoint organised into folders.

    • Test: creates folder based on the clash test name

    • Assignment: creates folder based on the individual assigned

    • Status: creates folder based on the clash status

    • None: no folders created

  4. Select the viewpoint types to include.

  5. Select the clash status that you want to create viewpoint for.

  6. Click Create viewpoints.