Add the unit-based columns to a Procore budget view
Background
The following source columns can be added to non-ERP standard budget views, enabling their use in calculated columns:
Standard Budget columns
Before you can track Productivity on your Budget, you must first set up three columns on the budget view that you want to use:Unit cost
Budget production
In Procore, a unit of measure (UoM) can be created to express these quantities for use with Procore’s Financial Management tools: time, amount, length, area, volume or mass. For example, hours, each, square metre.
Budget unit quantity
Source columns
Change event unit quantity (which can be used as filters for rough order of magnitude and revenue rough order of magnitude)
Direct cost unit quantity
Prime unit quantity
Timecard entry hours
For more information about creating calculated column, see Set up a new budget view.
Things to Consider
Required User Permissions:
'admin' on the company's Admin tool.
For companies using the ERP Integrations tool:
If you add the unit-based columns to the Procore enterprise resource planning direct cost Budget or any enterprise resource planning-integrated views, keep in mind that syncing the unit-based columns is NOT currently supported by Procore's
.In Procore, the term integrated ERP system, is used to refer to enterprise resource planning (ERP) software applications that can be configured to exchange data between Procore and a supported application using the Company level ERP Integrations tool. See which ERP integrations are supported by Procore.
Prerequisites
Create the budget view that you want to add the column to. See Set up a new budget view.
Steps
Navigate to the company's Admin tool.
Under Tool settings, click Budget.
Click Set up new budget view.
Under Standard views, select any non-ERP view in the list.
Click Create.
Click Configure columns.
Under the Standard columns list, place a tick next to the Budget unit cost, Budget UoM and Budget unit quantity.
Choose one of these options to create a Source column:
Click Create source column.
ORClick Create at the top right and choose Source from the drop-down menu.
Complete this data entry:
Column name. Type a name for your new column.
Column source. Select a unit quantity column from the drop-down list. For a list of fields, see Background above.
Configure options for the column you selected by marking the tickboxes for the column.
Click Create.
Click the X button to close the window when you are done working with it. The new column will now appear on your budget view and it will also be available to create calculated columns in reports.